Which of the following support the DSDM philosophy and principles?
Process, people, products and practices
People, products, phase and plans
Plans, projects, process and people
Phases, productivity, power and process
When should the quality of the evolving solution first be tesed?
At the end of a Timebox
At the end of a project.
At the end of each increment
As part of the iterative Development process
Identify the missing word in the following sentence.
The Business Sponsor is known as the project [?] because they are committed to the solution and the delivery approach.
Governor
Champion
Visionary
director
During what phase should the strategy for Iterative Development be considered?
Pre-Project
Feasibility
Foundations
Evolutionary Development