Weekend Special Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: clap70

AgilePM-Practitioner Agile Project Management (AgilePM) Practitioner Exam Questions and Answers

Questions 4

Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.

Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.

Each selection from Column 2 can be used once, more than once or not at all.

Column 1:

1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully

meet Hoy Hall requirements, after deployment.

2. Developing a fully functioning in-house system, developed and hosted by Architecture

Angels IT Operations team.

3. All-in-one web-based reservation and accommodation management system built to Hoy Hall's

specification.

4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group,

until a suitable system can be implemented at the site.

5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.

Column 2

    Maintainability is a required attribute of the initial delivered solution

    Deliver first, re-engineer later

    Short-term, tactical solution

Options:

Buy Now
Questions 5

Which 2 statements explain why the Architecture Angels' Marketing Director would be an appropriate Business Visionary?

Options:

A.

Is a friend of the Architecture Angels' Chief Executive.

B.

Is fully committed to changing the company's strategic direction to include hotel renovation.

C.

Is one of the original four founders of the company.

D.

As a Director, will ensure that the project is NOT driven by the cost-consciousness of the Finance Director in the role of Business Sponsor.

E.

Has a passion for old buildings and can see the potential for business opportunity.

Buy Now
Questions 6

Which 2 actions should the Workshop Facilitator take to implement the new

Must Have requirement?

Options:

A.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.

B.

Consolidate and circulate an agenda for the workshop.

C.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

D.

Assess the impact of the additional development costs on the original

Business Case.

E.

Encourage all parties to contribute, irrespective of their views.

Buy Now
Questions 7

Answer the following question about how risks will be reduced on the Hoy Hall Hotel project through successful application of the DSDM Principles.

Column 1 lists a selection of project risks identified on the Hoy Hall Hotel project. Column 2 is a list of the DSDM Principles. For each risk in Column 1, select from Column

2 the DSDM Principle which, if applied appropriately, would MOST help to reduce or mitigate that risk.

Each selection from Column 2 can be used once, more than once or not at all.

Options:

Buy Now
Questions 8

Which 2 actions should the Business Visionary take to implement the new

Must Have requirement?

Options:

A.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

B.

Assess the impact of the new Must Have requirement on the original

Business Case.

C.

Source and hire a web developer with experience in developing online

financial transaction functionality.

D.

Ensure the marketing and sales teams are working together to deliver the

most effective outcome.

E.

Consolidate and circulate an agenda for the workshop.

Buy Now
Questions 9

Which 2 actions should the Team Leader take to implement the new Must

Have requirement?

Options:

A.

Consolidate and circulate an agenda for the workshop.

B.

Add the additional tasks required to create the financial transaction

functionality to the Timebox Plan.

C.

Discuss the development interfaces and dependencies with the Solution

Development Team to ensure the associated Timebox is appropriate.

D.

Agree to de-scope Should Have and/or Could Have requirements to allow

for the new Must Have functionality.

E.

Source and hire a web developer with experience in developing online

financial transaction functionality.

Buy Now
Questions 10

Answer the following questions about the contents of the DSDM

products.

Each of the following questions includes true statements about the project

but only two statements are appropriate entries for the DSDM product

identified.

Remember to limit your answers to the number of selections requested in

each question.

Which 2 statements represent appropriate entries for the Business Case?

Options:

A.

A list of high-level functional and non-functional requirements that the

project should meet written as User Stories.

B.

Coffee shops that sell Fairtrade products and alcohol from local breweries

out perform other coffee shops in the market.

C.

The Sales Manager has been asked to produce a report within the next

two days showing the number of generic insurance policies sold to coffee

shops over the past three years.

D.

The Sales Manager has calculated that the new coffee shop insurance

product will increase revenues by 10% each week.

E.

Market research shows that the number of coffee shop patrons taking

legal action against retailers has increased by 200% over the past two

years.

Buy Now
Questions 11

Which 2 statements represent appropriate entries for the plan for Post-Project

activities?

Options:

A.

The Sales Manager will create a company-wide email showing the

number of policies sold weekly by each of the sales assistants.

B.

Before the product is deployed, the Sales Manager will circulate a copy of

the revised sales procedure for processing coffee shop insurance sales.

C.

The Project Manager will attend Daily Stand-up meetings to observe

progress.

D.

A report showing the number of application forms completed online

through the website for coffee shop insurance policies will be produced

weekly.

E.

Once the new system has been deployed, the time it takes to process

sales online will be compared with the time it takes to process new

policies sold through telephone sales.

Buy Now
Questions 12

The Web Content Manager has provided the Web Developer with a mock up

of the 'Contact Us' page, to be created for the new coffee bar insurance

product. When producing the code, the Web Developer has created a button

that reads 'Delete' instead of 'Cancel'.

What action should the Web Content Manager take?

Options:

A.

Prepare a defence for when the problem is identified, ensuring the

responsibility is with the Web Developer.

B.

Hide the problem and hope that this detail can be changed at a later date.

C.

Raise an issue to the Project Manager when the solution is deployed.

D.

Discuss the issue with the Web Developer and decide what action is

required to change this detail.

Buy Now
Questions 13

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following question

about assigning the Agile Project Management team roles within this

project.

Lines 1 to 5 in the table below consist of an assertion statement and a

reason statement. For each line identify the appropriate option, from options

A to E. that applies. Each option can be used once, more than once or not

at all.

Options:

Buy Now
Questions 14

Answer the following questions about the DSDM Lifecycle.

Decide if each observation is an appropriate application of Agile Project Management for

this project and select the option that supports your decision.

When the project was in the Feasibility phase it was initially proposed by the Finance

Manager that it was a fixed price for a fixed specification' project. The Project Manager

has decided that the best way to tackle it would be to leave the development of the least

valuable features of the product until last.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because the later parts of the project should reflect the least valuable features

of the product being built.

B.

Yes, because in a DSDM project there is no detailed specification upfront.

C.

No, because the Solution Development Team should decide which features are left

until last.

D.

No, because the most valuable features of the project should be delivered last.

Buy Now
Questions 15

Which 2 statements represent appropriate entries for the Development

Approach Definition?

Options:

A.

The Sales Manager will introduce an awards or bonus scheme, designed

to create competition between the sales assistants.

B.

Once deployed, the number of policies sold through traditional telephone

sales will be compared with the number of sales processed online

through the website.

C.

An easy to use web development tool called 'WebMatrix' is to be used to

develop and maintain the website extension.

D.

The Finance Director has requested a detailed report be produced after

12 weeks, showing costs to date and forecast cost to complete.

E.

Accessibility and performance of the new online quotation area is to be

tested using a tool called Sitebeam.

Buy Now
Questions 16

Time is running short and the Must Have requirements for the data entry screen

of the web page, as recorded in the Prioritised Requirements List, are not going

to be completed on time.

What action should the Project Manager take?

Options:

A.

Change the end date of the Timebox.

B.

Ensure that this issue is escalated to the project level roles.

C.

Amend the end date in the Delivery Plan.

D.

Accept that the Must Have requirements will not be delivered on time.

Buy Now
Questions 17

A difference of opinion on the outcome of an earlier project has created a

'them and us' culture between the Sales Department and the Operations

Department.

What action should the Project Manager take to resolve this?

Options:

A.

Allow the different skillsets to work independently of one another so as

not to create further conflict.

B.

Brief the team and the Business Visionary on the use of an Agile Project

Management approach and the requirement to collaborate.

C.

Appoint only those members of staff who are prepared to work

collaboratively.

D.

Circulate a copy of the Business Case to all members of the Solution

Development Team and project-level roles and invite feedback.

Buy Now
Questions 18

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Buy Now
Questions 19

An external web developer is to be contracted to create the new coffee bar

insurance area on the existing web site. The chosen web developer will only

agree to work on a 'fixed price for a fixed specification' contract.

What action should the Project Manager take?

Options:

A.

Ensure the later elements of the project reflect the most valuable features

of the product being built by the contractor.

B.

Agree to a 'fixed price for a fixed specification' contract with a requirement

for the web developer to provide daily progress reports.

C.

Refuse to employ the chosen web developer as this is not an Agile

approach to project management.

D.

Divide the work into component parts to ensure the web developer is

focused on, and is paid to deliver, only what is specified for each

component.

Buy Now
Questions 20

Xan Insurance Company operates from one location - a large, open-plan

office in the centre of a city. Those employees that will be working within the

Solution Development Team are all based in this office but work at different

ends of the office in separate departments.

What action should the Project Manager suggest to ensure the most effective

collaboration of the Solution Development Team?

Options:

A.

Create an email group for the Solution Development Team to collaborate

on ideas.

B.

Set up a telephone or video conferencing facility so that all members of

the team can collaborate effectively.

C.

Relocate these employees to a new project area, with a number of desks

where the Solution Development Team can sit together.

D.

No action required as these employees are located in the same office.

Buy Now
Questions 21

Using the Project Scenario, answer the following question about the activities in the Agile project lifecycle.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Assertion:-

1. The rooms and facilities must be deployed into live use at the end of each Timebox.

BECAUSE

Reason:

Evolutionary Development and Deployment must be combined in a Timebox where the integration of several teams is required.

2. The tasks associated with each Solution Development Timebox should be included

in the Delivery Plan.

BECAUSE

Reason:

A typical Delivery Plan will provide a schedule of Timeboxes and any other high level activities for the imminent Project Increment.

3. The development approach should have been agreed during Foundations.

BECAUSE

Reason:

The Development Approach Definition must be created before Evolutionary

Development can commence.

4. The resources from Timber Tigers and Earth Excavations should have been engaged

before the start of Evolutionary Development.

BECAUSE

Reason:

Commitment to delivery is based on pre-agreed resource levels at the project level.

5. A final Deployment phase should be held after Timebox C has completed.

BECAUSE

Reason:

The Deployed Solution is assessed post-project to confirm whether the expected benefits have been

achieved.

Options:

Buy Now
Questions 22

How should the Project Manager assist the plumbers to deliver the plumbing?

Options:

A.

Split the entire Solution Development Team into smaller teams covering specific locations of the house.

B.

Decide on the location of the radiators on behalf of Architecture Angels.

C.

Establish an inter-team competition to see which team can complete first.

D.

Approve each Timebox before work continues in the next.

Buy Now
Questions 23

The Business Sponsor threatened to stop funding if there was no evidence of tangible progress. To reduce this risk, the Business Sponsor was invited to several walk-

rounds of the new bedroom and en-suite bathroom facilities throughout the project.

Is this an appropriate application of Agile Project Management for this project?

Options:

A.

Yes, because the early and frequent demonstration of product features to the Business Sponsor increases the visibility of the project and keeps the business engaged.

B.

Yes, because the project's budget holder is the only person who can approve project products.

C.

No, because products should be handed over at the end of the project, during Post-Project.

D.

No, because the Daily Stand-up meetings should have allowed the key representatives to review and discuss the evolving solution.

Buy Now
Questions 24

How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?

Options:

A.

The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.

B.

The Solution Development Team should commence understanding and delivering the new requirement.

C.

The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels' Senior Management Team.

D.

The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.

Buy Now
Questions 25

During Timebox B, the 'Hoy for Hoy Hall'Action Group disagreed about the planned outcome of the Timebox. The Project Manager organised a Facilitated Workshop to re-

engage this group and explore discrepancies in understanding.

Is this an appropriate application of Agile Project Management for this project?

Options:

A.

Yes, because Facilitated Workshops provide a forum for each member of the team to present a short progress report.

B.

Yes, because discussing requirements in the presence of other stakeholders increases the whole group's awareness.

C.

No, because the Project Manager should have escalated this disagreement as an issue before any action was taken.

D.

No, because the local Action Group should have attended the Daily Stand-up meetings.

Buy Now
Questions 26

Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox

Plan for Timebox B?

Options:

A.

Marketing Director, in the role of Business Visionary.

B.

Team Leader.

C.

Project Manager and Architect, in the role of Technical Co-ordinator.

D.

Architecture Angels' Senior Management Team.

Buy Now
Questions 27

If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?

Options:

A.

Present own interpretation of what the system should include.

B.

Present the group with a predefined specification of what should be included.

C.

Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue.

D.

Agree to disagree, and close the workshop acknowledging that all participants are entitled to their own view.

E.

Prepare a report describing the outcome of the workshop.

Buy Now
Questions 28

Each of the following questions includes a list of true statements about individuals from Architecture Angels and Timber Tigers who have been appointed to the

project team. Only 2 statements explain why, in the context of an Agile team, the individual is a suitable candidate for that role.

Remember to limit your answers to the number of selections requested in each question.

Which 2 statements explain why the Architecture Angels' Finance Director would be an appropriate Business Sponsor?

Options:

A.

Is able to delegate most of the required involvement to the Chief Accountant.

B.

Has been friends with the Architecture Angels' Chief Executive since school.

C.

Is the project budget holder.

D.

Is concerned about preventing the costs of refurbishment from escalating and affecting the operations of the company.

E.

Will not distract the Solution Development Team, as is usually too busy to be involved.

Buy Now
Questions 29

Answer the following questions about applying the principles for building

engagement to the Change Programme, defined by Hodges.

Which 2 actions demonstrate inclusivity?

Options:

A.

Consider providing everyone at the next staff event with pens and notebooks with the UniCo logo and an image representing this change programme.

B.

Define in early key messages how the inclusion of Selco links to the strategic repositioning of UniCo in the marketplace.

C.

Encourage the team from Selco to continue to use their old logo as a way of maintaining some familiar symbolism they can identify with.

D.

Provide opportunities for staff who had volunteered to act as mentors during the Change Programme to meet to resolve resistance issues.

E.

Invite those staff who are asking questions about the Change Programme proposals to suggest what might work for them.

Buy Now
Questions 30

Answer the following question about Schein's concept of survival and learning

anxieties.

Column 1 is a list of messages about the change given to Sales staff. For each

message in Column 1, select from Column 2 the appropriate element of

Schein's concept of survival and learning anxieties. Each selection from

Column 2 can be used once, more than once or not at all.

Options:

Buy Now
Questions 31

Answer the following questions about using facilitation of a workshop to co-

design organizational change.

When facilitating a workshop to design a process, which recommendation is MOST likely to create a good solution?

Options:

A.

The focus should be on immediate action to reduce the organizational costs.

B.

The workshop should be held off-site to create independent thought.

C.

The participants should cover all elements of the process and its implementation.

D.

Only the senior decision-makers should attend to ensure implementation is viable.

Buy Now
Questions 32

Which 'event' BEST offers the opportunity to connect learning to the wider change initiative?

Options:

A.

Assess performance, testing whether the instruction has been effective.

B.

Provide guidance to support the learning process, such as real-life examples, stories, and discussion.

C.

Remind the learners of what they already know that is relevant to the current instruction (facts, rules, procedures, or skills).

D.

Provide good learning feedback that allows learners to evaluate their practice.

Buy Now
Questions 33

When receiving instruction on practical skills, which approach is MOST valuable to the learner?

Options:

A.

Practicing new skills until consistency is achieved.

B.

Observing repeated demonstrations of the skill by the instructor.

C.

Group discussion of how to learn the new skills.

D.

Presentation of how the new skills relate to the organizational change.

Buy Now
Questions 34

As time goes by, there is an increase in Customer Services staff asking questions about how their skills development will be supported under the new structure and how they will influence decisions about the projects they will be assigned to work on.

Which is the MOST appropriate response from the Customer Service Director?

Options:

A.

Prepare presentations to all staff outlining the targets for the new structure.

B.

Support line leadership roles on how to include those asking the questions.

C.

Ask for the communications from the change teams to include the questions.

D.

Define the approach and governance for the Customer Services projects.

Buy Now
Questions 35

The Change Manager is looking to develop the change agent network that will support the changes related to the Operational delivery processes workstream.

Which information is MOST likely to be relevant for the change agents when being inducted into the change programme for the Operational delivery processes workstream?

Options:

A.

Expected new ways of working for UniCo technical delivery.

B.

Staff contact details for the Operations department – UniCo and Selco.

C.

Annual UniCo staff satisfaction survey results.

D.

Portfolio, Programme, and Project Management Office Service Catalogue.

Buy Now
Questions 36

Which stakeholder should be placed within the 'primary' segment?

Options:

A.

Industry-related professional associations, whose strong opinions and judgments about industry trends reach wide audiences.

B.

The Utilities company, who selected UniCo to provide services but will dictate their specific requirements and operational terms.

C.

The Operations Director, who will consult with others to understand their requirements and decide on the approach.

D.

The UniCo investors, who have provided the finance to support the innovation and improvement needed to recover profitability.

Buy Now
Questions 37

Which information could be recorded on an ‘empathy map’ for the marketing staff?

Options:

A.

The Promotions Team Leader has noted that staff have raised concerns about how the change may reduce their sales during the seasonal promotions.

B.

The Marketing Manager has identified potential stakeholders, drawn symbolic figures of each of them and positioned them on a visual diagram.

C.

The Marketing analyst staff have made a list of potential stakeholders and plan to share this with everyone else at the next sales meeting.

D.

During a meeting of Brand Team Leaders, each participant created a list of stakeholders and then compared these lists in small groups.

Buy Now
Questions 38

Which participant characteristic is likely to be the MOST appropriate to the success of a workshop to design a process?

Options:

A.

They understand the culture of the organization.

B.

They have a good history of change implementation.

C.

They are confident in discussing ideas with others.

D.

They are willing to be involved and enthusiastic.

Buy Now
Questions 39

The Change Manager has mapped stakeholders onto a Power-Interest

Matrix, with the aim of identifying suitable actions for managing these

stakeholders.

The mapping below shows the current assessment made by the Change Manager.

The 'Interest in your change' axis indicates a combination of the

stakeholders' levels of active engagement and their buy-in for the Change

Programme.

Using the Scenario and the additional information provided for this question in the Scenario Booklet, answer the

following question about Stakeholder mapping and strategy.

Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each line identify the

appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Options:

Buy Now
Questions 40

To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.

Which 2 statements BEST explain why the IT Support Manager is appropriate for the role of change agent for the change programme?

Options:

A.

Is good at quietly implementing directions without challenging decisions at every step.

B.

Is well-positioned to bring together other line leaders facing similar change situations.

C.

Has a strong network due to supporting all staff at all levels organization-wide.

D.

Has direct line authority over the staff who will be changing internal IT systems.

E.

Wants to gain experience in change management to improve future implementations of IT systems.

Buy Now
Exam Name: Agile Project Management (AgilePM) Practitioner Exam
Last Update: Feb 22, 2025
Questions: 134
AgilePM-Practitioner pdf

AgilePM-Practitioner PDF

$25.5  $84.99
AgilePM-Practitioner Engine

AgilePM-Practitioner Testing Engine

$30  $99.99
AgilePM-Practitioner PDF + Engine

AgilePM-Practitioner PDF + Testing Engine

$40.5  $134.99