Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
At the beginning of Solution Development Timebox A, the Timebox is being
planned in detail. Although Foundations was conducted at a high level, the
Prioritised Requirements List was baselined. Now the Solution Development
Team is setting detailed acceptance criteria against each requirement.
Is this an appropriate approach to setting detailed acceptance criteria?
The project is now in the second week of Timebox C. This is the final Timebox of Project Increment 1 and is scheduled to take one month. The plan is to open
Hoy Hall to the public at the end of this Increment. A Must Have requirement of Timebox C is the implementation of a hotel reservation system.
At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.
However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video
tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of
storage space on the company server and require minimal maintenance.
The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.
Remember to limit your answers to the number of selections requested in each question.
Which 2 individuals should the Facilitator invite to participate in the Workshop?
Each of the following questions includes a list of true statements about individuals from Architecture Angels and Timber Tigers who have been appointed to the
project team. Only 2 statements explain why, in the context of an Agile team, the individual is a suitable candidate for that role.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements explain why the Architecture Angels' Finance Director would be an appropriate Business Sponsor?
Using the Project Scenario, answer the following question about the activities in the Agile project lifecycle.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
Assertion:-
1. The rooms and facilities must be deployed into live use at the end of each Timebox.
BECAUSE
Reason:
Evolutionary Development and Deployment must be combined in a Timebox where the integration of several teams is required.
2. The tasks associated with each Solution Development Timebox should be included
in the Delivery Plan.
BECAUSE
Reason:
A typical Delivery Plan will provide a schedule of Timeboxes and any other high level activities for the imminent Project Increment.
3. The development approach should have been agreed during Foundations.
BECAUSE
Reason:
The Development Approach Definition must be created before Evolutionary
Development can commence.
4. The resources from Timber Tigers and Earth Excavations should have been engaged
before the start of Evolutionary Development.
BECAUSE
Reason:
Commitment to delivery is based on pre-agreed resource levels at the project level.
5. A final Deployment phase should be held after Timebox C has completed.
BECAUSE
Reason:
The Deployed Solution is assessed post-project to confirm whether the expected benefits have been
achieved.
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The requirement to 'install a heat reclamation system' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.
Is this an appropriate action related to acceptance criteria?
The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the
agreement of the team.
Which Agile principle MOST influences this course of action?
Which 2 actions should the Team Leader take to implement the new Must
Have requirement?
Which 2 actions should the Technical Coordinator take to implement the new
Must Have requirement?
Which 2 statements represent appropriate entries for the Prioritised
Requirements List?
Which 2 statements represent appropriate entries for the Development
Approach Definition?
Column 1 is a list of individuals from within the Xan Insurance Company
and their key responsibility within the Web project.
For each individual in Column 1, select from Column 2 the Agile Project
Management team role they are fulfilling. Each selection from Column 2 can
be used once, more than once or not at all.
Column 1
Manager of Web & Digital
Media - will oversee and report
progress on the delivery of the
overall system.
Finance Director - has
budgetary control and will
release finance for the project
subject to expected benefits.
Sales Manager - will formulate
design options for new
business processes that do not
adversely affect business as
usual.
Operations Manager - oversees
the design and integrity of the
technical aspects of the
solution.
Column 2
Business Sponsor
Business Analyst
Business Ambassador
Business Advisor
Solution Developer
Technical Coordinator
DSDM Coach
Project Manager
Resources are limited. The Sales Manager has two marketing assistants who
may be able to give a few hours a week between them to the project.
What action should the Project Manager take?
Time is running short and the Must Have requirements for the data entry screen
of the web page, as recorded in the Prioritised Requirements List, are not going
to be completed on time.
What action should the Project Manager take?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a
reason statement. For each line identify the appropriate option, from options
A to E. that applies. Each option can be used once, more than once or not
at all.
Answer the following questions about actions to be taken by different
roles.
The Business Sponsor has decided that the new coffee shop insurance
product website pages will include the financial transaction functionality to
support the end-to-end sales process. The Business Sponsor views this as a
valuable sales tool, enabling customers to pay for insurance policies online. If
successful, this new financial transaction functionality is to be made available
across all other insurance products. This is a new Must Have requirement.
All parties are to be invited to a workshop to discuss the additional work
required to deliver the required solution including the new Must Have
requirement. The areas to be discussed include specialist skills required and
possible legal, financial and technical standards to be adhered to.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 actions should the Business Sponsor take to implement the new Must
Have requirement?
The Marketing Director has insisted that detailed requirements for the new
coffee bar insurance web pages should be clearly defined in the early phases
of the project.
What action should the Project Manager take?
The Web Content Manager has provided the Web Developer with a mock up
of the 'Contact Us' page, to be created for the new coffee bar insurance
product. When producing the code, the Web Developer has created a button
that reads 'Delete' instead of 'Cancel'.
What action should the Web Content Manager take?
The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time?