Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?
Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
Which of the following is a tool or technique used in the Determine Budget process?
The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:
Which of the following is a strategy to deal with positive risks or opportunities?
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:
The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
Which process determines the risks that may affect the project and documents their characteristics?
Which Process Group and Knowledge Area include the Sequence Activities process?
Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?
Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?
A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:
Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?
Which tool or technique is an examination of industry and specific vendor capabilities?
Which input to the Plan Risk Management process provides information on high-level risks?
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
Which of the following is an information gathering technique in Identify Risks?
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
Which technique is commonly used for the Perform Quantitative Risk Analysis process?
Which technique helps to determine the risks that have the most potential impact on a project?
Which of the following statements is true regarding project and product lifecycles?
Which of the following is an input to the Direct and Manage Project Execution process?
Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?
As the project progresses, which of the following is routinely collected from the project activities?
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
The following is a network diagram for a project.
The free float for Activity E is how many days?
The process of defining how the project scope will be validated and controlled is known as:
Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?
Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?
Which document in the project management plan can be updated in the Plan Procurement Management process?
One of the key benefits of the Plan Human Resource Management process is that it:
What is the number of stakeholders, if the project has 28 potential communication channels?
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?
Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?
Which organizational process assets update is performed during the Close Procurements process?
The integrative nature of project management requires which Process Group to interact with the other Process Groups?
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:
Which of the following tools or techniques is used for Estimate Activity Durations?
Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?
The creation of an internet site to engage stakeholders on a project is an example of which type of communication?
Work performance information and cost forecasts are outputs of which Project Cost Management process?
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
Which of the following is contained within the communications management plan?
The procurement process that documents agreements and related documentation for future reference is known as: