Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: geek65

C_TPLM22_67 SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 Questions and Answers

Questions 4

What is the procurement element for requirements planning?

Please choose the correct answer.

Response:

Options:

A.

Purchase requisition

B.

Purchase order

C.

Procurement plan

D.

Planned order

Buy Now
Questions 5

What are the prerequisites for automatic requirements grouping on the top WBS element of a project?

There are 2 correct answers to this question.

Response:

Options:

A.

The "project stock" indicator is set in the project definition (either valuated or non-valuated)

B.

The "Valuated project stock" indicator must be set in the project definition.

C.

The MRP group of the components must permit requirements grouping.

D.

The project must be released.

E.

The top-level WBS element must be released.

Buy Now
Questions 6

How do you optimize cash flows to maximize project profits and reduce project costs?

Please choose the correct answer.

Response:

Options:

A.

PS Cash management

B.

Mile stone billing

C.

Milestone management

D.

Billing plan

Buy Now
Questions 7

Which type of down-payment chain allows you to monitor receivables to customers and to gain information on past and future incoming payments?

Please choose the correct answer.

Response:

Options:

A.

Credit-side down payment

B.

Debit-side down payment

C.

Credit memo

D.

Debit memo

Buy Now
Questions 8

What are the three areas of the project screen?

There are 3 correct answers to this question.

Response:

Options:

A.

Structure tree

B.

Work area and template area

C.

Task list area

D.

Work area

Buy Now
Questions 9

Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing?

There are 2 correct answers to this question.

Response:

Options:

A.

Activate milestone functions.

B.

Activate indicator sales document date for milestones.

C.

Create a billing plan assigned to a sales order item.

D.

Set up percentage of completion for milestones.

E.

Create a billing plan assigned to a WBS element.

Buy Now
Questions 10

How can you update the degree of processing for an activity?

Options:

A.

By charging the activity

B.

By confirming the activity

C.

By using results analysis

D.

By scheduling the activity

Buy Now
Questions 11

Which of the following determines the account assignment category in sales order item?

There are 2 correct answers to this question.

Response:

Options:

A.

Requirements class

B.

Requirements type

C.

Requirement category

D.

Requirement function

Buy Now
Questions 12

Which indicator automates the grouping of project stock assigned to individual WBS elements to the top WBS element?

Please choose the correct answer.

Response:

Options:

A.

Project stock indicator

B.

Requirements indicator

C.

Project element indicator

D.

Automatic requirement grouping

Buy Now
Questions 13

What are the different views available for capacity planning and work center planning?

There are 2 correct answers to this question.

Response:

Options:

A.

Work center view

B.

Capacity planning view

C.

Periodic view

D.

Project view

Buy Now
Questions 14

You are using the billing and down payment processing in Sales and Distribution and updating the actual data to billing elements in the project system.

Which of the following business processes can be mapped in Sales and Distribution?

There are 3 correct answers to this question.

Response:

Options:

A.

Fixed down payment amounts and fixed milestone billing amounts

B.

Fixed down payment amounts and resource-related milestone billing amount

C.

Resource-related down payments and milestone billing amount

D.

Milestone billing of budgeted WBS elements

E.

Milestone billing of statistical WBS elements

Buy Now
Questions 15

Which type of billing is generally used in plant engineering and construction projects?

Please choose the correct answer.

Response:

Options:

A.

Periodic billing

B.

Project billing

C.

Milestone billing

D.

Fixed billing

Buy Now
Questions 16

Which type of order is created at BOM level to cover requirements when a material shortage occurs in material planning?

Please choose the correct answer.

Response:

Options:

A.

Scheduled orders

B.

Procurement orders

C.

Planned orders

D.

Stock orders

Buy Now
Questions 17

Which of the following are controlled using plant and order type parameters?

There are 2 correct answers to this question.

Response:

Options:

A.

Number assignment

B.

If the network is assigned to an activity or header

C.

Default value settings

D.

The settlement rule strategy

Buy Now
Questions 18

What are the components on which reporting is based upon, in profit center accounting?

There are 2 correct answers to this question.

Response:

Options:

A.

Cost centers

B.

Cost elements

C.

Profit centers

D.

Profit center hierarchy

Buy Now
Questions 19

What is the flag used for WBS elements for which you want to plan costs?

Please choose the correct answer.

Response:

Options:

A.

Planning elements

B.

Assignment elements

C.

Billing elements

D.

Revenue elements

Buy Now
Questions 20

What are the different types of assembly orders that can be created?

There are 3 correct answers to this question.

Response:

Options:

A.

Plant order

B.

Network order

C.

Plant maintenance

D.

Process order

Buy Now
Questions 21

Which type of confirmation allows you to enter the actual start and finish date,forecast finish date and forecast work in a tabular format?

Please choose the correct answer.

Response:

Options:

A.

Individual confirmation

B.

Single confirmation

C.

Collective confirmation

D.

Group confirmation

Buy Now
Questions 22

To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?

There are 2 correct answers to this question.

Response:

Options:

A.

Billing element

B.

Cost element

C.

Pricing element

D.

Account assignment element

Buy Now
Questions 23

For which objects can billing plans be created? (2)

Options:

A.

Activities

B.

Sales order items

C.

WBS elements

D.

Milestones

E.

Project definition

Buy Now
Questions 24

Which scenario does not allow you to access the project team of the higher-level WBS element during “workforce planning”?

Please choose the correct answer.

Response:

Options:

A.

If a WBS element does not have its own project team

B.

If a WBS element does have its own project team

C.

WBS element is in the higher level

D.

Project team is in the higher level in hierarchy to WBS element

Buy Now
Exam Code: C_TPLM22_67
Exam Name: SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7
Last Update: Nov 21, 2024
Questions: 165
C_TPLM22_67 pdf

C_TPLM22_67 PDF

$28  $80
C_TPLM22_67 Engine

C_TPLM22_67 Testing Engine

$33.25  $95
C_TPLM22_67 PDF + Engine

C_TPLM22_67 PDF + Testing Engine

$45.5  $130