Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: geek65

C_TS422_2023 SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Questions and Answers

Questions 4

Which time elements are relevant for lead time scheduling of a production order? Note:

There are 2 correct answers to this question.

Options:

A.

setup time

B.

Opening Period

C.

Float after Production

D.

Total replenishment lead time

Buy Now
Questions 5

Advanced Planning uses master data and transaction data from SAP S/4HANA In which data objects can you set the Advanced Planning flag?

Note: There are 2 correct answers to this question.

Options:

A.

Work Center

B.

Production Version

C.

Material

D.

plant

Buy Now
Questions 6

In documentation for MRP in Advanced Planning, you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?

Options:

A.

MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.

B.

MRP assigns the capacity requirements automatically after the last scheduled order on a work center.

C.

MRP creates the capacity requirements without checking the work center capacities.

D.

MRP creates the capacity requirements only if the work center has sufficient capacity.

Buy Now
Questions 7

which SAP application can be used for forecasting in Supply Chain Planning?

Note: there are 2 correct answers to this question.

Options:

A.

Integration Business Planning (IBP)

B.

Capacity Requirement Planning (CRP)

C.

Supply Chain Management (SCM)

D.

Material Requirement Planning (MRP)

Buy Now
Questions 8

What could be the reason for multiple commitments, where several operations have the same scheduled dates on a work center after dispatching?

Note: There are 2 correct answers to this question.

Options:

A.

The Finite Scheduling indicator is NOT set in the strategy profile.

B.

The work center has several individual capacities

C.

The Change Planning Direction indicator is set in the strategy profile

D.

Alternative work centers are fully occupied.

Buy Now
Questions 9

Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

Options:

A.

To increase the number of planning levels

B.

To simplify the structure of bills of material

C.

To reduce the number of material masters

D.

To make the assignment of components easier

E.

To reduce the number of changes required in bills of material

Buy Now
Questions 10

What will happen in the MRP run if you have created a new MRP-relevant material that

supports both in-house production and external procurement?

Options:

A.

The MRP run assumes external procurement.

B.

The MRP run assumes in-house production.

C.

The MRP run does NOT consider the material; it has to be planned interactivelty

D.

The MRP run plans the material only if a quotation has been maintained.

Buy Now
Questions 11

Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA. When can you use mode selection?

Options:

A.

When multiple production versions are maintained for one product

B.

When multiple operations are maintained for one product

C.

When alternative resources are used within one operation

D.

When multiple planned orders exist on one resource

Buy Now
Questions 12

Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

Options:

A.

Use a propagation range.

B.

Use a resource group

C.

Use a planning area.

D.

Use a planning group.

Buy Now
Questions 13

Which business processes are affected by settings in the order-type-dependent parameters?

Note: There are 2 correct answers to this question.

Options:

A.

Check material availability.

B.

Schedule production orders.

C.

Define integration with cost accounting.

D.

Select master data.

Buy Now
Questions 14

Your project team decided to use a make-to-order planning strategy material in discrete manufacturing.

what is the impact of this decision?

Note: there are 2 correct answers to this question

Options:

A.

Storage Location MRP areas are required for sales-orders-specific stock.

B.

Net requirement calculation is carried out for every sales order individually.

C.

Both the reduction of make-to-order stock and requirements occur on delivery

D.

Sales orders have to be ATP-confirmed (available-to-promise) to saved.

E.

Production orders are created with sales order reference.

Buy Now
Questions 15

For a production version to be valid and consistent, what requirements must be fulfilled? Note: There are 3 correct answers to this question.

Options:

A.

The deletion flag must NOT be set for the bill of material (BOM) or the routing

B.

The lot size range must be within the lot size range of the assigned routing.

C.

The assigned routing and bill of material (BOM) must be valid in the entirevalidity period.

D.

The assigned routing must be a rate routing.

E.

The assigned routing must NOT have alternative sequences

Buy Now
Questions 16

Your company produces a finished good based on a forecast and expects it to be in stock when customers order it. If customers order more than the forecasted quantity, this must NOT have any impact on the production program. Which planning strategy do you use?

Options:

A.

Make-to-stock production (10)

B.

Planning with final assembly (40)

C.

Make-to-stock production (20)

D.

Planning without final assembly (50)

Buy Now
Questions 17

What data can you maintain in the subitems of a bill of material (BOM)?

Note: There are 2 correct answers to this question.

Options:

A.

Installation point

B.

Item type

C.

Quantity

D.

Scrap percentage

Buy Now
Questions 18

What are some benefits of planning with planned independent requirements? Note: There are 2 correct answers to this question.

Options:

A.

Reduced production times

B.

Reduced delivery times

C.

Option to use make-to-order production

D.

Option to forecast planning for production resources

Buy Now
Questions 19

You use planning strategy Finite Scheduling with Reverse and want to allow scheduling the past. How can you parameterize this in the strategy profile?

Options:

A.

Specify a negative planning horizon.

B.

Specify a positive planning horizon.

C.

Specify a positive offset time.

D.

Specify a negative offset time.

Buy Now
Questions 20

What does forecasting in the demand planning cycle include?

Note: There are 3 correct answers to this question

Options:

A.

One-off events

B.

Past quotation quantities

C.

Past sales order quantities

D.

Market intelligence

E.

Past production planning quantities

Buy Now
Questions 21

You want to reduce planning efforts for B and C materials. Which planning procedure do you recommend?

Options:

A.

Manual Planning Without Check

B.

Consumption-Based Planning

C.

Material Requirements Planning

D.

Advanced Planning

Buy Now
Questions 22

where does the system check master data selection settings during the creation of planned orders and production orders?

Note: There are 3 Correct answers to this question.

Options:

A.

in the bill of material (BOM)

B.

in the work centers

C.

in the MRP controller

D.

In the routing

E.

in the production version

Buy Now
Questions 23

What can you use heuristics in Advanced Planning (PP/DS) for?

Options:

A.

To optimize costs and times in production plans

B.

To solve planning problems for defined objects

C.

To automate material movements in material staging

D.

To set default values in production master data

Buy Now
Questions 24

What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.

Options:

A.

Order type

B.

Planning strategy

C.

Requirements profile

D.

Requirements type

Buy Now
Exam Code: C_TS422_2023
Exam Name: SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing
Last Update: Sep 15, 2024
Questions: 80
C_TS422_2023 pdf

C_TS422_2023 PDF

$28  $80
C_TS422_2023 Engine

C_TS422_2023 Testing Engine

$33.25  $95
C_TS422_2023 PDF + Engine

C_TS422_2023 PDF + Testing Engine

$45.5  $130