C_TS422_2023 SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Questions and Answers

Questions 4

You are trying to create a production order NO valid production version can be selected. What could be the reasons? Note: There are 2 correct answers to this question.

Options:

A.

The order lot size is NOT within the validity range of a production version.

B.

NO production lines are assigned to the production versions.

C.

All production versions for the material are locked.

D.

NO bills of material (BOMs) are assigned to the production versions.

Buy Now
Questions 5

In documentation for MRP in Advanced Planning you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?

Options:

A.

MRP assigns the capacity requirements automatically after the last scheduled operation for each work center.

B.

MRP creates the capacity requirements without considering existing load on the work centers.

C.

MRP creates the capacity requirements at the earliest possible time.

D.

MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.

Buy Now
Questions 6

How are dependent requirements for assemblies created? Note: There are 2 correct answers to this question.

Options:

A.

They are created together with the independent requirement for the finished product.

B.

They are created on assembly level during the planning run.

C.

They are created with exact times in Advanced Planning.

D.

They are only created for multilevel bill of material (BOM) structures.

Buy Now
Questions 7

Advanced Planning uses master data from SAP S/4HANA Cloud Private Edition. In which data objects can you set the Advanced Planning flag? Note: There are 2 correct answers to this question.

Options:

A.

Work center

B.

Plant

C.

Production version

D.

Material

Buy Now
Questions 8

Which business processes are affected by settings in the order type dependent parameters? Note: There are 2 correct answers to this question.

Options:

A.

Schedule production orders.

B.

Check material availability.

C.

Select master data.

D.

Define integration with cost accounting.

Buy Now
Questions 9

What could be the reason for different combinations of components in a multiple bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

Manufacturing date

B.

BOM header status

C.

BOM component status

D.

Lot size

Buy Now
Questions 10

How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question.

Options:

A.

By capacity planning

B.

By order confirmation

C.

By order release

D.

By mass processing

Buy Now
Questions 11

Where does the system check master data selection settings during the creation of planned orders production orders? Note: There are 3 correct answers to this question.

Options:

A.

In the production version

B.

In the work centers

C.

In the bill of material (BOM)

D.

In the MRP controller

E.

In the routing

Buy Now
Questions 12

What options does a planner have in the planning table for repetitive manufacturing? Note: There are 2 correct answers to this question.

Options:

A.

Change the assignments of production quantities to production lines.

B.

Create new production quantities.

C.

Dispatch operations to work centers.

D.

Reschedule deallocate operations.

Buy Now
Questions 13

Your project team decides to use a maketoorder planning strategy for a strategic material in discrete manufacturing. What are the impacts of this decision? Note: There are 3 correct answers to this question.

Options:

A.

Net requirements calculation is carried out for every sales order individually.

B.

Production orders are created with sales order reference.

C.

Storage location MRP areas are required for salesorderspecific stock.

D.

Both the reduction of maketoorder stock requirements occur on delivery.

E.

Sales orders have to be ATPconfirmed (availabletopromise) to be saved.

Buy Now
Questions 14

Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.

Options:

A.

Production orders

B.

Planned orders (firmed)

C.

Planned orders (unfirmed)

D.

ATP quantities

Buy Now
Questions 15

What does a line hierarchy in repetitive manufacturing represent?

Options:

A.

A production line with more than one work center

B.

A production line with an alternative sequence in the routing

C.

A production line with a parallel sequence in the routing

D.

A production line with prioritized alternative work centers

Buy Now
Questions 16

What are the advantages of collective orders? Note: There are 2 correct answers to this question.

Options:

A.

To perform availability checks across the entire collective order

B.

To coordinate orders in the planning board for a collective order

C.

To show the flow of batches across the entire collective order

D.

To post confirmations for the entire collective order

Buy Now
Questions 17

What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.

Options:

A.

You can reschedule the operation using lead time scheduling.

B.

You can reschedule the operation using infinite scheduling in a planning table.

C.

You can reschedule the operation using finite scheduling in a planning table.

D.

You can reschedule the operation in the Manage Work Center Capacity app.

Buy Now
Questions 18

Which information is required when you create a product master in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.

Options:

A.

Base unit of measure

B.

Industry sector

C.

Selection screen for views

D.

Product type

Buy Now
Questions 19

What is a work center hierarchy?

Options:

A.

A group of alternative work centers for production structured in hierarchy levels by priorities

B.

A group of alternative work centers providing a cumulative available capacity for production

C.

A group of work centers in a production line being used in sequence for production

D.

A group of work centers in a parallel sequence that is used to split production quantities work on them in parallel

Buy Now
Questions 20

Where do you maintain the work center that represents the production line for repetitive manufacturing? Note: There are 2 correct answers to this question.

Options:

A.

Production cost collector

B.

Production version

C.

Repetitive manufacturing profile

D.

Routing

Buy Now
Questions 21

How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

By material type

B.

By plant

C.

By period

D.

By material status

Buy Now
Questions 22

What are the prerequisites for a reporting point confirmation in repetitive manufacturing? Note: There are 2 correct answers to this question.

Options:

A.

Activating the reporting point backflush in the order dependent parameters

B.

Activating the reporting point backflush in the work centers

C.

Defining the relevant work centers in the routing

D.

Defining the operations as reporting points using the control key

Buy Now
Questions 23

Your company produces a finished good based on a forecast expects it to be in stock when customers order it. If customers order more than the forecasted quantity this must NOT have any impact on the production program.

Which planning strategy do you use?

Options:

A.

Assembly processing with production orders (82)

B.

Planning with final assembly (40)

C.

Planning without final assembly (50)

D.

Maketostock production (10)

Buy Now
Questions 24

Which time elements does MRP consider in backward scheduling to determine the basic dates for components from depender Note: There are 2 correct answers to this question.

Options:

A.

Planned delivery time

B.

Total replenishment lead time

C.

Operation duration

D.

Inhouse production time

Buy Now
Exam Code: C_TS422_2023
Exam Name: SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing
Last Update: Nov 21, 2024
Questions: 80
C_TS422_2023 pdf

C_TS422_2023 PDF

$28  $80
C_TS422_2023 Engine

C_TS422_2023 Testing Engine

$33.25  $95
C_TS422_2023 PDF + Engine

C_TS422_2023 PDF + Testing Engine

$45.5  $130