Your test team has created a custom automation tool that will be used for an upcoming release. Now that the tool has been coded, what
should be the next step? [1]
Your team has been given the following test objective Ensure that the users are happier with this version than they were with the last version?
What is wrong with the way this is defined?
Your team has been working on an Agile project for two months. There is a retrospective at the endof each sprint One of the data items reviewed is how many defects are being caught by users rather than by testers. The test team is being blamed for these escapes
What do you need to do to make these sessions more productive?
Your manager has decided that your team of manual testers should all become test automation engineers Your team is much stronger in analysis than In technical testing so you are concerned about their ability to adapt. What tool capabilities could help with this transition?
When scheduling performance testing, which of the following approaches would be most advisable? [1]
You tend to be conservative in your project estimations because you know how many things can go wrong and extend the schedule. You manager is not happy with your estimates and thinks you are being too negative with your numbers and not trying hard enough Which estimation method should you use to provide your manager with a positive' number while still also providing the number you think is more realistic?
You are managing the testing for a bank card project. The testing was scheduled to take 10 weeks but by the time the software was developed only six weeks were available for testing Knowing there were a lot of risks with the software your team started testing activities early by overseeing code reviews, defining acceptance criteria by working with the users and by doing all lest creation prior to the code arriving
You are now three days away from the go-live date Your testing has mitigated all the high and medium risk items leaving only the low-risk elements unmitigated by testing You estimate it will take two weeks to manually test the low-risk elements At this point what should you do?
You are a new lest manager in an organization You have been asked to assess the defect process to determine if there are any efficiency improvements that could be made that would reduce the cost of quality You have started digging through the defect Information What information would be most helpful for this investigation?
Your defect opened trend is converging to the closed trend but there is still a gap. What does that gap represent?
You feel that your team has become lazy when applying good software testing techniques You have given each of them a challenge to take a different business rule and build a full decision tableand then collapse that table You will then assess the results For this assessment, what competencies are you validating?
Which of the following is required to apply an experience-based testing approach''
You are working on a project that is having problems with regressions. With each release of software given to the test team. 50% of the defects found are actually regressions. To combat this you have decided to implement test automation. You have given your automation team the following goal
'Implement lest automation to automate 90% of the manual regression tests before the product release date.’’
Which of the following is likely an issue with this goal being defined as "SMART?
It the lest manager must repeatedly step in to resolve conflicts within the team what phase is the team in and what competencies are required from the test manager?
You have been asked to estimate the testing effort for an upgrade to a legacy product Your team did the testing on the last upgrade, and you have ascertained that this upgrade is about 10% bigger than the last one Given this information which estimation technique should you use to come up with the test effort number?
Which of the following Is considered a heavyweight risk-based testing technique'
You have assembled the following cost of quality numbers 1 000 defects were found prior to release and 100 were found after.
Given this information what should you conclude?
Your organization has decided to augment your testing team with an offshore team. The offshore team members are experienced testers who are experts in the domain of the system under test Your team is worried about the offshore team taking their jobs and they are resistant to the change You need to pick three of your team members to be the ambassadors for the new team
Which competences will be most important for your ambassadors to possess?
You are working for an outsource testing company You have a client that will only consider candidates that are highly skilled with Salesforce. regardless of the number of years they have spent testing similar products You have looked through your skills matrix and you have no one with the right type of experience for this project.
What competence area is your team lacking?
You have been asked to make a recommendation on deployment readiness on the software your team has been testing.You have the following metrics:
Given this information what is a critical metric you are missing?
You are a Test Manager and have started a program of test process improvement. You are following the IDEAL model and have completed the first three phases, now you are ready to go further. Which TWO of the following activities will enable you to complete the remaining phases of the IDEAL model?
You are managing the test team that is testing a new mobile application that provides a "step-by-step' hiking guide Your risk assessment resulted in the following table:
Your team has clone the depth and breadth testing for the GPS accuracy and usability features but when the product was given to beta testers there were some issues Despite the users reporting the app was easy to use at least one user walked off the edge of a cliff and another one ended up in a river. Your team has confirmed that the functionality is working correctly. and the GPS information is accurate.
What other area of testing should you now prioritize?
Your team has decided that they will build their own test management tool This will allow them to link the requirements and test cases together providing full traceability It will also allow them to create fully customized reporting and color-coded dashboards They have estimated the time required to create the new tool and the cost These fit within the project schedule and budget
What other consideration should be taken before this decision is made?
At what testing level do the test management activities Include coordinating with end users7
You have assembled the following cost of quality numbers 200 defects were found prior to release and 100 were found after.
Given this information what is the total cost of quality for this project?
Refer to SCENARIO 3
You are the Test Manager for a software house called "MakeMyApp" that specialise in mobile phone applications, agile techniques are used for all software development projects.
A new project is underway to develop enhancements to a 'photo sharing' application, known as 'PictureFriend'. There are two types of user account available -Premium Users and Guest Users. Guest users only have limited functionality available. The enhanced features to PictureFriend are:
• Feature 1: Guest Users can share photos with other Guest Users and Premium Users;
• Feature 2: Premium Users can edit pictures before posting to their account;
• Feature 3: Premium Users can create '3D-effect' photographs
The requirements for each feature will be broken down into a number of User Stories with acceptance criteria created for each of them. User Stories are planned and delivered in 2-week 'Sprints'. The project will have 3 sprints.
Which of the following are test planning activities that would be MOST appropriate for Sprint 1?
a) Analyse the risk for each of the user stories in sprint 1
b) Publish lest progress reports throughout the sprint
c) Arrange informal reviews of the user stories by the test team
d) Plan an automated system test suite for the user stories.
e) Specify system test conditions at a detailed level for all user stories Chose one of the following options:
SELECT ONE OPTION
You have been looking at the actual vs expected defects in one high risk area of the software The actual is much higher than the expected value What should you do?
You have been assigned t o a project that has a very tight schedule. In fact, given your first analysis you do not think the planned test execution can be completed within the schedule There is no time allowed for defect fixing or for repeating tests. Regression testing has been left out of the planning entirely There is no time to develop test automation. The team has agreed that this Is not the way to run a project, yet they are stuck with the current schedule
Given this information what is the best way to proceed with the testing to try to meet the deadline with the best outcome1?
You are working with a development team who have a CI/CD pipeline implemented. They want to integrate your team's existing test automation into the pipeline to augment their unit tests so they will have continuous testing. They have already determined that this is technically possible with the tool you are using but with require some changes to the test automation framework to integrate the results reporting
What will your team need to make this happen?
Which of the following Is the common set of information to be produced in a test estimate''
You have just conducted a skills assessment for your team. You decided to rate everyone from 1 to 5 in the skill areas as follows:
5 = expert
4 = proficient
3 = can use this skill effectively but will need some assistance
2 = interested in learning this skill but has only minimal knowledge
1 = not interested in learning this skill
Given these values, you have rated your team as shown in the table below for the designated skill areas:
You will be starting to test a new product that is an upgrade from one of your existing end user products. Your testing will include white box,
performance, security, usability, and black box. You also have a goal to automate 100% of the smoke test and 50% of the regression tests by the end of the release.
Your team willingly shares knowledge and conducts regular lunch time cross-training sessions.
Your manager wants to know if you would like to bring in someone to help train your team in preparation for this project. In which area could
you best utilize this help? [3]
In an Agile project, when Is it acceptable lo not write a formal defect report when a defect is found''
Your team has been assigned to lest a new product that is tightly integrated with existing systems The integrations include data transfers and transformations You have access to the architectural design documents and the integration specifications and some of your testers are former developers.
Given this information, what is the most appropriate test approach?
You have replaced informal code reviews with technical reviews for the most complex and critical components, in an attempt to reduce the high number of defects being found during component and integration test levels. The project manager is concerned about the costs of implementing formal reviews and has asked you to measure whether they actually provide a return on investment.
Which three of the following metrics would be MOST effective in helping you to achieve this?
a. Identification of defect clusters across components
b. Number of lines of code reviewed
c. Number of defects found during reviews d Root cause for each defect detected
e Post-review cost of detection and internal failure per defect
f. Type of review
g. Effort to conduct the review including rework
You have initiated a test process improvement project for your organisation using the STEP model. You have agreed the objectives, goals, scope and coverage of the process improvements with the stakeholders and defined the success criteria that will be applied to the project. Success criteria make risk reduction the most important target benefit for the process improvements, but overall return on investment is also an important consideration. You have just received the initial test
assessment report.
Which ONE of the following would be the next step? SELECT ONE OPTION
You are the Test Manager on a project to replace an old sales and merchandising system with one that will be based on modern platforms It will be developed using an Agile lifecycle.
The main requirements for the system are:
Loading sales data, sent electronically from the stores each evening, into a central database.
Producing sales reports for the merchandisers, whose job is to manage stock levels in stores.
Producing forecast reports, used to predict demand for each product, based on a combination of sales history and forecasting parameters. The parameters will be entered by the merchandisers into a browser based front end and the reports will be produced overnight.Requirements 1 and 2 are satisfied by the existing system and will be rewritten with no significant changes. Requirement 3 is new.The Data Centre Manager is concerned about the performance of overnight batch processing and the Sales and Merchandising Manager is concerned about usability. Both managers have indicated that they are keen to allocate resources to acceptance testing.You have already determined that component and component integration testing will be done by developers before any other testing.
Which option contains TWO items that would complete your test approach in respect of test levels?
Refer to SCENARIO 2 - You have been tasked with recruiting testers for Project 3 to help design and run regression tests, you have been provided with a skills matrix for four prospective candidates. The matrix shows the skill level (High or Low) for each candidate:
Which candidate would be the MOST suitable for a test analyst role on Project 3?
SELECT ONE OPTION
Refer to SCENARIO 2 It has been agreed that the following test planning documents will be produced;
• A single overarching document outlining the general testing methodology for the whole programme of work
• A subordinate test plan for each of the three projects
• A separate test plan for performance testing within each project
Which one of the following options BEST describes the type of test management document that will meet the programme requirements?
When closing out a defect report, which of the following developer commentaries is most likely to motivate a tester? [1]
You are assigned to test a new application being developed in-house and you have designed a set of test cases to specifically address key product risks. You will issue daily reports summarising how these test cases are progressing during test execution. When considering the audience for these reports, in which stakeholder matrix quadrant would the product's users reside?
Assume that you are working for a company that has maintained and tested a car parking permit system for many years. The system holds the name and address of permit holders and automatically writes to the permit holder with a form to renew or cancel their permit each year.
The test plan states the following:
"since the system is considered a stable system. Boundary Value Analysis is the only test case design technique that needs to be applied during testing"
Consider the following change that was detailed in the Requirements Specification for a replacement to an existing parameter held within the system;
• The specified renewal date for each permit must be not be after 31 st January 2020. Which one of the following is a valid test condition that satisfies both the requirement and the test plan?
SELECT ONE OPTION
Which one of the following is NOT a determining factor when considering the optimal time to conduct a document review? SELECT ONE OPTION
You are Test Manager working on a project which is improving the user interface for its call centre staff handling customer enquiries. The project has completed UAT for the first iteration; however a large number of defects were raised by call centre staff seconded to help with the User Acceptance testing.
The defects described the user interface as not being intuitive enough with a poor 'help' facility. A user representative spent a week working with developers and system testers to explain the issues, which were subsequently agreed to have resulted from poorly specified usability requirements.
The requirements were defined separately for each iteration and have been formally reviewed by business analysts, developers and the IT director.
The user representative was also able to answer a number of other questions that the system test team had regarding call centre workflows, which improved their domain knowledge.
You have been asked to conduct a project retrospective and recommend improvements for the next iteration which introduces further user interface changes. Which of the following would be the MOST effective improvement for the next iteration?
You are preparing the estimate for the test plan, which should cover all test activities subsequent to the plan having been agreed. Estimation of test activities has in the past been embarrassingly inaccurate. Historical data from previous similar projects is unreliable, but for two recent projects it is possible to find out how many test cases were developed and how long this took.
Which TWO of the following estimation techniques will be BEST in this scenario?
You have directed one of your testers to construct a "smoke test" to execute against new builds prior to starting formal testing. This is an example of which software development lifecycle activity?
[1]
The teams are two days away from the end of the current iteration. The rate at which users have been reporting defects has been trending upward in the last few weeks and so far during this latest iteration has shown another increase.
The scrum master of the team responsible for most defects has asked you for ideas about how to perform the next retrospective in order to learn the appropriate lessons.
You have suggested that they should provide the retrospective meeting with a breakdown, by nature and severity, of the defects relevant to that team.
Assuming that this is done, which next three steps of the retrospective will be MOST effective?
Which of the following BEST explains how test process improvement can benefit an organisation? SELECT ONE OPTION
Which two of the following activities would normally occur in the Acquisition stage of a tool's lifecycle?
a) Assign a tool administrator to decide on best use of the tool
b) Establish a backup and restore strategy for the tool
c) Review other tools provided by the same vendor
d) Determine how the tool may be impacted by a change to the operating environment
e) Develop and implement a training plan for new users of the tool
SELECT ONE OPTION
You are Test Manager of a project delivering a workflow system for complex business processes It has been decided a tool is required to increase the efficiency of test execution. What would be a valid issue to consider when deciding whether to build a custom made tool?
SELECT ONE OPTION
Referring to SCENARIO 2 It has been agreed that Project 1 will be delivered using an Agile approach, with user stories delivered across three sprints, each lasting 4 weeks. The programme manager is concerned about RISK 3 and wants the Master Test Plan to specify an effective test process improvement approach.
Which of the following is the best test process improvement approach for Project 1 ? SELECT ONE OPTION
Consider the following metrics:
a Percentage of all product risks identified during initial risk analysis
b. Average time taken by developers to fix defects for each severity level
c. Statement coverage achieved by the component test suite
d. Breakdown of defects detected by test level
How many of the five primary dimensions for test progress monitoring have been addressed by these metrics?
SELECT ONE OPTION
You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but
it is clear that the project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development
team.
At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of the delivered product and will be
watching the project closely, particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate
for all test cases covering risks that are classified as "high" or "very high", 95% pass rate for all "medium" risks and 75% pass rate for all "low" and "very low" risks.
Given this information, which of the activities of the standard test process are the most critical for the Test Manager to perform? [3]
You are the Test Manager of a risk-based testing effort. You develop the following graph to show residual risk. Assume that "Risks mitigated" represents passed tests and "Risks not mitigated"
represents failed tests and other discovered failures.
Which of the following answers best represents what the graph shows? [3]
Which two items are MOST important for inclusion in your tool selection plan for batch-only performance testing?
Which of the following metrics would be most beneficial to collect to determine the effectiveness of a review process? [2]