Month End Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: clap70

IDPX Interior Design Professional Exam Questions and Answers

Questions 4

During construction, the general contractor notices conflicting information between the construction drawings and the specifications. The FIRST step the contractor should take is to

Options:

A.

issue a change order

B.

make an interpretation

C.

notify the owner of the discrepancy

D.

notify the designer of the discrepancy

Buy Now
Questions 5

Design time has exceeded what was estimated when determining the fixed-fee contract. Whatshould be done?

Options:

A.

Proceed with fees designated in the contract

B.

Negotiate a new contract and fee agreement

C.

Stop work until a new agreement can be negotiated

D.

Attach time sheets to the invoice to clarify additional fees

Buy Now
Questions 6

During demolition, the contractor discovers dry rot in some existing walls that are to remain. After reaching an agreement with the client and contractor on a solution, what should be issued before construction continues?

Options:

A.

a bulletin

B.

an addendum

C.

a change order

D.

a change directive

Buy Now
Questions 7

A conflict on the job site impacts the location of a wall sconce, requiring an adjustment. The BEST way to communicate this change is for the

Options:

A.

interior designer to request the electrical engineer issue a change order

B.

interior designer to provide a sketch as part of a supplemental instruction

C.

general contractor to request a change directive prior to making a change

D.

electrical engineer to issue an addenda as part of the contract documents

Buy Now
Questions 8

Administration, marketing, and management expenses in a design firm are examples of

Options:

A.

Indirect labor

B.

Billable hours

C.

Direct materials

D.

Facility overhead

Buy Now
Questions 9

A designer has been hired to design millwork for a school library. During installation, there is a conflict between existing field conditions and shop drawing dimensions. Who is responsible for the discrepancy?

Options:

A.

Installer

B.

Manufacturer

C.

Interior designer

D.

General contractor

Buy Now
Questions 10

The role of the project manager includes

Options:

A.

selecting a project team, establishing and overseeing the budget, and coordinating withconsultants

B.

preparing preliminary designs, coordinating with consultants, and developing proposals and contracts

C.

serving as the primary client contact, developing proposals and contracts, and producing project specifications

D.

establishing and overseeing the budget, producing schematic designs, and serving as the primary client contact

Buy Now
Questions 11

What do written specifications define?

Options:

A.

quantity

B.

form

C.

quality

D.

relationship

Buy Now
Questions 12

What is the MAXIMUM occupant load of a business occupancy with one exit?

Options:

A.

49

B.

50

C.

69

D.

70

Buy Now
Questions 13

What provision should a designer include in the contract to minimize liability in claims that arise from delays caused by other project members?

Options:

A.

An exclusion of liability for delays caused by other project members

B.

A realistic project schedule with deadlines for each phase of the project

C.

A specified number of months the contract is in force, with a renewal clause

D.

Language excluding the designer from delay-related errors and omissions liability

Buy Now
Questions 14

What are the three parts of a Construction Specification Institute (CSI) specification?

Options:

A.

general, products, execution

B.

allowance, alternate, application

C.

information, purchasing, installing

D.

requirements, finishes, construction

Buy Now
Questions 15

A designer is planning an office remodel where the tenant is relocating their existing microwaves. After project completion, the tenant is disappointed to discover the outlets for the microwaves were installed at the incorrect height. What could the designer have done to prevent this?

Options:

A.

Coordinated the outlet heights with the electrical drawings

B.

Requested an appliance submittal from the general contractor

C.

Scheduled a site walk with the electrical contractor during installation

D.

Verified the equipment specifications with the microwave manufacturer

Buy Now
Questions 16

Which two functions are allowed with a one-hour fire separation in a fully-sprinklered building?

Options:

A.

a bank and a theater

B.

a car wash and a bank

C.

a theater and a casino gaming floor

D.

a casino gaming floor and a bowling alley

Buy Now
Questions 17

When the owner/contractor agreement is executed, which documents specifically form the contract documents?

Options:

A.

drawings, specifications, instruction to bidders

B.

drawings, specifications, addenda

C.

specifications, addenda, bid (tender) solicitation

D.

addenda, bid (tender) solicitation, instruction to bidders

Buy Now
Questions 18

During a substantial completion walk-through, a designer notices that a door was installed incorrectly. What should the designer do NEXT?

Options:

A.

Meet with the general contractor, review the drawings, and schedule replacement

B.

Process a change order and include the new door location

C.

Add the door location and problem to the punch (deficiency) list

D.

Ask the client to accept the door, with a credit memo

Buy Now
Questions 19

What is the MINIMUM fire rating for a door in a 2-hour fire separation wall?

Options:

A.

3/4-hour

B.

1-hour

C.

1 1/2-hours

D.

2-hours

Buy Now
Questions 20

The designer attends the weekly progress meetings and is responsible for the meeting minutes. How does the designer ensure that the minutes prepared are accurate?

Options:

A.

Issue a clause in the minutes indicating that minutes are approved and accepted as written

B.

Issue minutes including a clause stipulating minutes will be approved within 24 hours of issue

C.

Issue minutes including a clause enabling attendees to submit revisions within a specified time frame

D.

Issue draft minutes within 24 hours of the meeting, followed by final minutes within 72 hours of meeting completion

Buy Now
Questions 21

What is required prior to occupancy to improve indoor air quality?

Options:

A.

clean the air intake vents

B.

run the mechanical system

C.

test carbon monoxide detectors

Buy Now
Questions 22

What is one way to reduce indoor air pollutants?

Options:

A.

increase humidity levels

B.

install operable windows

C.

use materials with high VOCs

D.

decrease building temperature

Buy Now
Questions 23

A residential client wants to build an addition that would occupy the entire side-yard. What is the interior designer responsible for checking before proceeding?

Options:

A.

soils report

B.

access route

C.

setback requirement

D.

neighborhood agreement

Buy Now
Questions 24

In a soft goods furniture specification, what information should always be included?

Options:

A.

Fabric specification

B.

Installation instructions

C.

Location of the item on the plan

D.

Furniture vendor’s contact information

Buy Now
Questions 25

Upon completion of a project, what documents would the designer retain for their files?

Options:

A.

Record (as-built) drawings and specifications

B.

Post-occupancy evaluation and specifications

C.

Record (as-built) drawings and inspection report

D.

Post-occupancy evaluation and inspection report

Buy Now
Questions 26

After completion of a project, the client spills coffee on their new lobby sofa. Where would the client look for information on how to remove the stain?

Options:

A.

product data sheet

B.

warranty information

C.

maintenance manual

D.

furniture specification

Buy Now
Questions 27

Prior to the contract document phase, a designer should meet with a client for what purpose?

Options:

A.

Having the client understand and approve the finalized drawing layout

B.

Determining what the client’s overall budget is for non-fixed furnishings

C.

Reviewing and giving the client the written proposals for all items to be purchased

D.

Submitting copies of the furniture specifications the designer will be sending to vendors

Buy Now
Questions 28

What should be evaluated by the design team in advance of a project kickoff with clients and stakeholders?

Options:

A.

Cost analysis and value engineering

B.

Site availability and schedule impacts

C.

System performance and subcontractor availability

Buy Now
Questions 29

A university is renovating the restrooms (washrooms) of a dormitory built in 1963 and is required to reduce the water usage by 20%. What is MOST important when specifying plumbing fixtures?

Options:

A.

durability & Green Seal fixtures

B.

cleanability & Energy Star fixtures

C.

accessibility & WaterSense fixtures

D.

sustainability & International Plumbing Code compliant fixtures

Buy Now
Questions 30

In an existing non-sprinklered multi-tenant building, a client will be converting a suite from a bank into a restaurant serving more than 49 persons. What fire rating is REQUIRED between the new tenant and the existing adjacent insurance office?

Options:

A.

0

B.

1

C.

2

D.

3

Buy Now
Questions 31

Any space that is classified as an assembly occupancy MUST have

Options:

A.

the occupancy load posted

B.

a dedicated restroom (washroom)

C.

direct access to the main elevator

Buy Now
Questions 32

Information regarding product substitutions is found in the

Options:

A.

bid (tender) forms

B.

general requirements

C.

material specifications

Buy Now
Questions 33

The specification of which item is within the scope of work for interior designers when designing for water conservation?

Options:

A.

ultra-low flow faucets

B.

vegetated roof system

C.

rainwater collection cisterns

D.

FSC certified wood products

Buy Now
Questions 34

Which of the following would allow for ease of reconfiguration of power and data for open office environments?

Options:

A.

access flooring

B.

poke-through system

C.

cellular floor systems

D.

underfloor steel ducts

Buy Now
Questions 35

To reduce radon levels in a home, it is recommended that the

Options:

A.

crawl space is ventilated

B.

building is depressurized

C.

basement windows are sealed

D.

expansion joints are installed at slabs-on-grade

Buy Now
Questions 36

What should a designer recommend to BEST save on construction costs in a corporate office project with a tight improvement allowance?

Options:

A.

Reuse the existing doors and millwork where possible

B.

Save as many existing nonstructural walls as possible

C.

Maintain the existing water closet and lavatory locations

D.

Design an open-plan for each space without suspended ceilings

Buy Now
Questions 37

Plumbing traps are an essential feature of sanitary drains because they prevent

Options:

A.

the backflow of wastewater

B.

the backflow of sewer gases

C.

the contamination of water supply with wastewater

D.

the contamination of water supply with sewer gases

Buy Now
Questions 38

A building code official has declined to issue a building permit for a project. The official explains that the plans and specifications do not meet code in terms of partition fire ratings and finishes. In order to keep the project on schedule, what would be the FIRST step in dealing with the problem?

Options:

A.

File an appeal with the city

B.

Notify the client immediately

C.

Notify the contractor by phone

D.

Discuss the problem with the code official

Buy Now
Questions 39

Delivery of product directly to the client’s address is known as

Options:

A.

pro forma

B.

sidemarked

C.

drop shipped

D.

freight on board

Buy Now
Questions 40

A project is running behind schedule and over budget. What should the designer do FIRST?

Options:

A.

Review and determine budget cuts with the client

B.

Simplify installation methods to save both cost and time

C.

Contact the client to discuss the problem as soon as possible

D.

Rank construction priorities and complete the critical path elements first

Buy Now
Questions 41

The project team is reviewing a mock-up of a faux plaster ceiling finish. The mock-up is a 4'x4' board on an easel in the contractor’s construction trailer. What should the designer request?

Options:

A.

A larger mock-up with the adjacent wall and light fixture finishes

B.

Three mock-ups with different shades of plaster and softer ambient lighting

C.

To view the sample horizontally from below and with lighting similar to the design

Buy Now
Questions 42

What is the rentable square footage [m²] of a building?

Options:

A.

the tenant suite not including any common and shared areas of a building

B.

the tenant suite including all of common areas of a building such as lobbies, corridors, hallways and restrooms (washrooms)

C.

the tenant suite including a percentage of common areas of a building such as lobbies, corridors, vertical penetrations, hallways and restrooms (washrooms)

D.

the common and shared areas of a building such as lobbies, corridors, stairwells, meeting rooms, hallways and restrooms (washrooms) used by all building tenants

Buy Now
Questions 43

What would be included as part of a fire separation (fire assembly)?

Options:

A.

Dampers

B.

Operable window

C.

Low flame-spread rating

D.

Flame retardant wallcovering

Buy Now
Questions 44

While on site, the designer notices that the glazing subcontractor is installing the storefront system in the wrong finish. What should the designer do?

Options:

A.

Report the discrepancy in a memo to the contractor and client

B.

Reach out to the glazing supplier to find out which finish was ordered

C.

Explain the issue at the next owner, architect, contractor (OAC) meeting

D.

Tell the subcontractor to stop their work and explain the issue to the contractor

Buy Now
Questions 45

When developing a design, which BEST unifies the project and provides specific direction for the design?

Options:

A.

Feasibility studies

B.

Concept statement

C.

Space allocation studies

D.

Programming and research

Buy Now
Questions 46

An interior designer was contacted by their client shortly after occupancy and move-in, complaining that lights in private offices and some spaces were turning off automatically after a few minutes. What is the BEST next step?

Options:

A.

Inform the client that they can disconnect the occupancy sensors

B.

Reconfigure the spaces with issues to better improve occupancy sensor line-of-sight

C.

Have the occupancy sensors replaced with manual switches at the owner’s expense

D.

Contact the installer to check that the occupancy sensors are set to the maximum time limit

Buy Now
Questions 47

Upon review of all consultants’ drawings, the designer notices that the placement of a water closet is not consistent with the contract documents. What should the designer do?

Options:

A.

Provide the dimensions of the water closet along with a notation on the interior design documents of the water closet’s new location

B.

Coordinate the proper location with all parties through a change order

C.

Coordinate with the mechanical engineer and have the water closet relocated on the engineer’s drawings

D.

No action is necessary because the contractor is obliged to follow the interior design documents

Buy Now
Questions 48

Several employees in an office suffer from pollen allergies. How could their symptoms be reduced while at work?

Options:

A.

Install non-operable windows

B.

Install high-efficiency air filters

C.

Utilize a passive ventilation system

D.

Relocate these employees to internal offices

Buy Now
Questions 49

What type of space may employees be relocated to during a phased remodel project?

Options:

A.

swing

B.

staging

C.

hoteling

D.

pre-move

Buy Now
Questions 50

A designer is working on a joint venture project with a local engineering firm for a large university project. What drawing system will BEST incorporate coordination of project information?

Options:

A.

Facility condition index (FCI)

B.

Building information modeling (BIM)

C.

Project life cycle management (PLM)

D.

Virtual design and construction project manager (VDC)

Buy Now
Questions 51

Why is corrective work completed post-occupancy often MORE costly for the contractor?

Options:

A.

The warranty has expired

B.

Progress payments are not included

C.

The work must be performed after hours

D.

Revisions are billed on a cost-plus basis

Buy Now
Questions 52

The ground floor of a building contains a mixed occupancy with a retail store (9,500 sf [884 m²]) with an adjacent storage space (2,000 sf [186 m²]), a daycare (5,000 sf [465 m²]), and an office (6,000 sf [557 m²]). Based on the chart below, what is the occupant load for this floor?

Occupancy Type

Occupant Load Factor (sf/person)

Retail (Mercantile)

60

Storage

300

Daycare

35

Office (Business)

150

Options:

A.

305

B.

368

C.

524

D.

527

Buy Now
Exam Code: IDPX
Exam Name: Interior Design Professional Exam
Last Update: Apr 24, 2025
Questions: 175
IDPX pdf

IDPX PDF

$25.5  $84.99
IDPX Engine

IDPX Testing Engine

$30  $99.99
IDPX PDF + Engine

IDPX PDF + Testing Engine

$40.5  $134.99