A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?
One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?
During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?
Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?
A software development team completed the development and testing of a new accounting software system for a client. Which of the following should the team do next?
During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should the Program manager take?
The project manager sends individual messages to team members about what must be accomplished. However, the team communicates confusion about the tasks assigned. Which of the following communication methods would be best to use?
During a project kickoff meeting, the project manager wants to set expectations for all of the team members. Which of the following actions should the project manager take to accomplish this goal?
Which of the following would help a project manager identify that project goals have been reached?
A project team evaluates the potential risks to a project that uses legacy applications. Which of the following should be the main concern of the project team?
A company is adapting its strategy almost every quarter, and the product might be different at the end of the project. Which of the following is the best methodology for the project manager to use?
A project manager is reviewing quality planning techniques. Which of the following involves comparing results of similar activities?
Which of the following provides a layered approach to logging in to systems that contain an organization ' s most valuable intellectual property?
Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users ' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?
A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?
Which of the following is available after a project closes and the solution is handed over to the business team and put into production?
Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?
During project initiation, a project manager needs to establish the communication channel that will be used to deliver weekly presentations to stakeholders who are across the country. Which of the following would be the best communication channel to use?
During project initiation, a project manager is drafting a document that includes an outline of the high-level goals, objectives, milestones, and requirements. This document will be modified and finalized as more information becomes available. Which of the following best meets the requirements?
During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.
INSTRUCTIONS
Review the email with the latest updates sent by the project sponsor and respond in
the following order:
1. Select the best tool for tracking the server migration progress.
2. Select the new critical path.
3. Select the correct number of engineers required for the server migration phase.
If at any time you would like to bring back the initial state of the simulation, please click
the Reset All button.
Select the Appropriate Tool:


Select the new critical path.
Option A
Option B
Option C

Which of the following best describes a manufacturer ' s obligation to repair or change, without extra costs, any part of a product that is not functioning?
A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

Which of the following most likely represents the number of items in the backlog?
A project scheduler updates the project status with the following information: SPI = 1.25 and CPI = 0.85. Which of the following can the project manager infer about the current project status?
A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?
A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?
A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:
• Two developers
• High uncertainty about existing systems
• Risk of frequent requirement changes
• Tight deadlines
Which of the following project methodologies would be best to use in this situation?
Functional managers are reluctant to provide a project manager with resources for a project because they think the project should include a certain scope. The project manager reviews the project documentation and confirms the items the functional managers wanted to include were out of scope. Which of the following would be the best course of action for the project manager to take?
A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?
Which of the following concepts represents multiple resources interfaced to run reports?
Which of the following BEST describes how an organization should coordinate management of multiple related projects?
A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?
During the testing phase of a project, an executive raises a concern about a missing requirement in the product. Which of the following is the next step the project manager should take?
A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?
A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?
A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).
During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?
The project team identifies a risk of delayed materials on a project in a remote location. Which of the following actions can the team take to transfer the risk?
The project manager must create a project charter. Which of the following should be included in the charter?
A project sponsor requires a system that is capable of providing integrated management of all the business ' s core functions. Which of the following systems is the project sponsor describing?
A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project ' s production run will be delayed from the beginning.
Which of the following dependencies is most likely happening?
A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager ' s objective for the vendor meeting?
A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?
A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?
Which of the following metrics BE ST measures the alignment of the information security program to operational objectives?
A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?
A team member needs to make an emergency update. The team member is unable to return to the office. Which of the following is the most secure way to make the update?
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
A company wants to move its data from on premises to off premises. Which of the following cloud models should be pursued?
Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?
A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?
During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?
During an active project, the finished product is not meeting quality specifications Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?
A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?
Which of the following situations would require a project manager to revise the communication plan during a project ' s execution?
A client continues to present the project team with additional changes. To help with agreeing upon an expected delivery date, the project manager sets up a meeting with stakeholders. Which of the following should this meeting identify?
A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Select two).
A project manager working in a strong matrix organization was selected to manage a new project with trending technologies. During the kickoff meeting, one of the stakeholders mentions that the company has never worked with such technologies. Which of the following should the project manager do next?
Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?
A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?
An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?
As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world Which of the following should the project manager consider doing as part of the project planning?
During a steering committee meeting, members of the meeting decide to implement several proposed suggestions. Which of the following documents should be updated first as a result of this decision?
A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:
During a functional validation exercise, two end users request changes to the product that cannot be implemented without altering the already constrained project budget. The project manager convinces the end users to simplify the change request so it can be accomplished. Which of the following conflict resolution techniques did the project manager use?
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?
During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?
A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:

Based on the chart, which of the following is the current status of the project?
During a PMO audit, an auditor notices a discrepancy between the existing financial report and the financial information provided by the project manager at the end of the project in the previous quarter. Which of the following activities would have most likely avoided this discrepancy?
A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
A system is scheduled to go live, and the client signed an SLA. Which of the following elements is part of the agreement?
A project manager is managing a virtual team across the country. As reported in the retrospective, the team morale has decreased due to additional production issues. Which of the following meeting tools is the best option to record results in the retrospective?
A project manager has noticed that one-hour status calls are consistently lasting an extra 10 to 15 minutes. Which of the following techniques would be best for the project manager to use?
After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?
A manufacturing company is experiencing a high number of defects in its products and wants to identify the root cause to improve its processes Which of the following should the company use?
Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?
The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?
The sales department accidentally has access to all project files, including employee personal information. Which of the following security concepts is this violating?
A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?
Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?
During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?
A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable solution. Which of the following outcomes would most likely occur?
A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?
A project manager is meeting with stakeholders to identify objectives and success criteria. Which of the following artifacts is the project manager working on?
Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?
A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?
Which of the following contract types in project procurement has the highest risk for the buyer?
A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?
Which of the following best explains why companies apply background screening during the employment process?
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?
A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?
A financial manager reports that several employees ' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?
A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to
identify the level of engagement among project team members. Which of the following would be the best tool for the project manager to use?
Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?
After releasing an application into production, a major defect is detected. The project team implements a work-around that fixes the issue for now. Which of the following should the team do next?
Given the following chart showing committed work (orange) vs. actual work completed (blue) across 10 sprints:

Which of the following best describes the team ' s performance?
A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?
Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?
Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?
During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?
Which of the following is the best alternative to allow multiple users to edit a project plan in real time?
A project manager makes a list of the smallest activity components in the project. Which of the following is the project manager building?
A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?
A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?
Which of the following should a product manager choose in order to enable collaboration between team members located in different regions? (Select two).
A new project manager takes over a project midway through the schedule. Which of the following should the project manager do first before continuing the project?
Given the following network diagram:
Which of the following is the critical path?
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?
A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?
Which of the following considers factors such as reliability, scalability, security, and cost-effectiveness within project goals and objectives?
Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?
An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?
A)

B)
C)

D)

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?
A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?
After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?
In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?
A project manager would like to add external engineers to the current team. Engineers will participate in specific tasks only during the testing phase. Which of the following contracts would the project manager most likely use in this situation?
A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?
A company is designing a new ERP system. The SOW includes modules for different departments. During a meeting, a stakeholder requests an additional feature. Which of the following action should the project manager take next?
The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project’s level of compliance with the budget. Which of the following best describes what the project manager should do to assist the client?
A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?
A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).
A stakeholder raises a concern that a certain important functionality might be missing and asks the PM to submit a change request so it can be included. The PM is confident the functionality is included. Which of the following has the PM most likely checked?
A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?
Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?