A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?
A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?
During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?
During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?
Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).
A project manager is leading the implementation of a new service for a well-known, global company for which brand image is most important. The project will rely on contracted services. As part of the request for proposal process, the project team has identified a short list of vendors to submit proposals. Which of the following items should the project team consider as a primary factor to remove a vendor from consideration?
A project team evaluates the potential risks to a project that uses legacy applications. Which of the following should be the main concern of the project team?
Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?
A senior PM is working on the development of a tax application and focuses efforts to create an environment to facilitate and motivate teamwork. The team members seem to be in the storming phase. Which of the following best describes the team life cycle?
After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?
Which of the following would a scrum team discuss during a daily stand-up meeting?
Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?
A team found a deficiency in an application and is proposing improvements, but the sponsor requests a business case. Which of the following best describes the intended objective of the business case?
A project team is running into challenges because members are unclear about other members' roles. Which of the following charts should the project manager create?
An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?
A project misses a deadline. The project manager creates the following diagram:
Execution: The change control process was not followed. The customer added requests for previously unrequested features. The team developed unnecessary features.
Requirements: The customer did not provide all requirements during the initiation phase.
Which of the following is most likely the root cause of the delay?
A product manager is producing a project status report for key stakeholders Which of the following should most likely be included? (Select two).
A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?
A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM most likely perform?
During schedule planning, a project manager determined the logical dependencies required to complete the project. Which of the following activities should the project manager do next?
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
Which of the following best describes a program in the context of project management?
A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)
As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world Which of the following should the project manager consider doing as part of the project planning?
A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?
Which of the following contract types in project procurement has the highest risk for the buyer?
A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?
A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?
Which of the following is a consideration when determining a project's ESG factors?
While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?
Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?
A project manager is concerned about the performance of a developer who is struggling with the new coding language. Which of the following actions should the project manager take?
A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?
Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?
A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?
A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.
Which of the following is the current status of the process?
A team member is not completing deliverables on time or responding to emails while the project manager is on vacation. Which of the following actions should the technical lead take?
Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?
During a gate review meeting, the deliverable was rejected by the customer.
INSTRUCTIONS
Review the dashboard.
• Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
• Part 2: Select the proper document(s) to be updated.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.
Part 1:
Part 2:
A project team member wrote a user guide over the past ten days. Given the following scatter diagram.
Which erf the following can be formally conducted?
Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?
After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?
Which of the following should be considered first when determining the privacy management for project data?
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?
During quality analysis, different team members are identifying multiple constraints. Which of the following tools should the project manager adopt first to help track and prioritize a resolution?
Which of the following software programs would be best to use to store information related to business transactions?
During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?
A project manager working in a strong matrix organization was selected to manage a new project with trending technologies. During the kickoff meeting, one of the stakeholders mentions that the company has never worked with such technologies. Which of the following should the project manager do next?
During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?
Which of the following software programs would be BEST to use lo store information related to business transactions?
Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?
During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:
Average worked hours
Which of the following describes the result?
The project team identifies a risk of delayed materials on a project in a remote location. Which of the following actions can the team take to transfer the risk?
While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources. Which of the following risk responses does this demonstrate?
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
Which of the following is the most important activity for the project manager during the closure of a project?
While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?
A project manager and team are currently in the planning phase of a project. Which of the following should the team do during this phase?
During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?
During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?
A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?
A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do next?
A stakeholder raises a concern that a certain important functionality might be missing and asks the PM to submit a change request so it can be included. The PM is confident the functionality is included. Which of the following has the PM most likely checked?
Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?
During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?
A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:
Which of the following most likely represents the number of items in the backlog?
A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?
A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?
A project sponsor tells the project manager that new regulatory environment changes are coming in the next month. Which of the following should the project manager do next?
Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?
A project manager requests the testing team to figure out if a website allows multiple users to be signed in at the same time. Which of the following testing methods would be best for the testing team to use?
A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?
A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?
As a result of an unpredicted risk, a project manager is documenting a request in the change control log. Which of the following change control processes should the project manager do last?
Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?
A highly scored negative risk causes a risk trigger, but the issue has not started yet. Which of the following is the next step the project team should take?
After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?
During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the following would best align with these needs?
A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?
During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?
A project manager is reviewing quality planning techniques. Which of the following involves comparing results of similar activities?
A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?
A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?
During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?
A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?
When assigning access, classifying information based on sensitivity is referred to as:
A software engineer notices that the newest update to the reporting software includes many new features that were not defined in the requirements document. Which of the following steps should the engineer take next?
A member keeps bringing up unrelated topics during a team meeting. Which of the following should the protect manager do to keep the discussion on track?
Which of the following activities should a project manager perform during the closing phase? (Select three).
Given the following network diagram:
Which of the following is the critical path?
Which of the following should a product manager choose in order to enable collaboration between team members located in different regions? (Select two).
A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?
In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?
A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?
A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?
A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?
During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should the Program manager take?
While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?
A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to
identify the level of engagement among project team members. Which of the following would be the best tool for the project manager to use?
Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?
Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?
While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?
Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?
The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?
A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?
An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?
A team member identifies a critical issue in production. Which of the following should the project manager apply?
A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Select two).
Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?
A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?
A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?
Which of the following concepts represents multiple resources interfaced to run reports?
A project manager needs to develop a way to control who can modify documents, artifacts, and other data related to the product. Which of the following would be the best way to accomplish this objective?