Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: clap70

PRINCE2-Agile-Foundation PRINCE2 Agile Foundation (Version 2) Exam Questions and Answers

Questions 4

Which statement about quality tolerances for a product is CORRECT in an agile context?

Options:

A.

All quality criteria tolerance must be fixed

B.

Quality tolerances should be the same for all quality criteria

C.

Setting quality tolerance relies on prioritising quality criteria

D.

All quality criteria should have zero tolerance

Buy Now
Questions 5

How is the ‘tailor to suit the project’ principle applied in an agile context?

Options:

A.

By flexing what is produced to stay in control and deliver value

B.

By emphasizing tolerances on what is being delivered

C.

By using the Agilometer to assess the project environment

D.

By fitting releases into planned management stages

Buy Now
Questions 6

Which is a responsibility of the product owner?

Options:

A.

Monitor progress of the stage

B.

Ensure project-level risks are identified and assessed

C.

Prepare and maintain the project backlog

D.

Prepare and maintain the product backlog

Buy Now
Questions 7

In which area is Agile strongest when blending with PRINCE2?

Options:

A.

Product delivery

B.

Project management

C.

Project direction

D.

Product management

Buy Now
Questions 8

Why are team working agreement produced?

Options:

A.

To create structure so that the team manager can assess individual performance

B.

To evolve the effectiveness and behaviors of the self-organizing team by agreeing values

C.

To make the team rules visible to the project manager for monitoring purposes

D.

To ensure that the delivery team members comply with company policy

Buy Now
Questions 9

What should be emphasized when tailoring the PRINCE2 Progress theme?

Options:

A.

Monitoring what is being delivered

B.

Tracking time and cost

C.

Planning resources

D.

Assessing the impact of risks

Buy Now
Questions 10

Which of the following uses a flow-based approach to control work in progress?

Options:

A.

Agilometer

B.

Lean

C.

Kanban

D.

Scrum

Buy Now
Questions 11

To help with prioritization, what is MOST important when understanding the difference between scope and quality?

Options:

A.

Combining functional and non-functional requirements

B.

Creating non-functional requirements with user stories

C.

Differentiating functional from non-functional requirements

D.

Defining non-functional requirements before functional requirements

Buy Now
Questions 12

Which statement about the ‘embrace change’ target is CORRECT?

Options:

A.

It re-establishes team dynamics when a new member joins the team

B.

It trades user stories for those of a similar size

C.

It results in the late delivery of the minimum viable product

D.

It degrades the performance of the features that are delivered

Buy Now
Questions 13

How should a minor quality control failure during the creation of a product be addressed initially?

Options:

A.

By escalating the issue to the project manager

B.

By performing an independent review of the product

C.

By revisiting the development and test activities

D.

By discussing with the chief product owner

Buy Now
Questions 14

What is an epic?

Options:

A.

A low-level requirement

B.

A fine-grained user story

C.

A detailed feature

D.

A high-level requirement

Buy Now
Questions 15

What challenge does PRINCE2 Agile address in Agile adoption?

Options:

A.

Agile frameworks are too rigid for product delivery

B.

Agile frameworks struggle to scale for large, complex initiatives

C.

Agile frameworks struggle with role definitions

D.

Agile frameworks cannot be combined with other methods

Buy Now
Questions 16

Which of the following defines agility?

Options:

A.

The set of activities that define the sequence of actions

B.

The ability to embrace and respond to change

C.

The ability to protect from uncontrolled changes

D.

The core belief that anyone is capable of learning

Buy Now
Questions 17

What is an epic?

Options:

A.

A detailed user story with high business value

B.

The set of products handed over to the users

C.

A high-level user story that is quite broad or vague

D.

A prioritized list of requirements to be delivered in a sprint

Buy Now
Questions 18

Which workshop focuses on team growth and improvements in working practices?

Options:

A.

Project kickoff workshop

B.

Team retrospective workshop

C.

Progress review workshop

D.

Team planning workshop

Buy Now
Questions 19

What is typically displayed on a board to show progress to people working on a project?

Options:

A.

Agilometer assessment

B.

Product backlog

C.

Information radiator

D.

User story

Buy Now
Questions 20

Which statement explains how the ‘learn from experience’ principle is applied in an agile context?

Options:

A.

It focuses on the prioritization and decomposition of requirements

B.

It integrates releases within management stages

C.

It is supported by the ‘inspect and adapt’ concept

D.

It provides guidance on mapping PRINCE2 roles to an agile environment

Buy Now
Questions 21

Which two statements about tailoring the business case in an agile environment are CORRECT?

1. It should be unnecessary because products of the highest value will be delivered first.

2. It should identify the minimum viable product and when it will be delivered.

3. It should take into account that the scope may be reduced during the course of the project.

4. It should show the features, the order in which they will be delivered and any dependencies.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 22

What is the purpose of the “agile enablement” workshop?

Options:

A.

To identify, assess, and plan for risks associated with project delivery

B.

To identify, assess, and plan for risks associated with team delivery

C.

To identify, assess, and plan for risks associated with Agile adoption

D.

To identify, assess, and plan for risks associated with enterprise agility

Buy Now
Questions 23

What information is NOT typically displayed on a burn chart?

Options:

A.

Effort remaining

B.

Team working agreements

C.

Actual amount of work done

D.

Amount of time elapsed

Buy Now
Questions 24

Which statement explains the PRINCE2 Agile behavior of ‘exploration’?

Options:

A.

It empowers the project management team at the delivery level

B.

It uses the most effective channel to communicate information

C.

It displays the progress rate to everyone using burn-down charts

D.

It seeks out feedback collaboratively from project stakeholders

Buy Now
Questions 25

Which process can take place during a release review workshop?

Options:

A.

Controlling a stage

B.

Managing product delivery

C.

Managing a stage boundary

D.

Directing a project

Buy Now
Questions 26

What is the MOST important when blending PRINCE2 Project Management with agile?

Options:

A.

Adopting agile mindset

B.

Fostering psychological safety

C.

Using agile techniques

D.

Following agile processes

Buy Now
Questions 27

In which process should the requirements for delivery of specialist products be agreed?

Options:

A.

Initiating a project

B.

Managing product delivery

C.

Starting up a project

D.

Managing a stage boundary

Buy Now
Questions 28

During which process should release planning be done for the FIRST time?

Options:

A.

Initiating a project

B.

Managing a stage boundary

C.

Managing product delivery

D.

Controlling a stage

Buy Now
Questions 29

Why is Lean Startup included in the ‘starting up a project’ process in PRINCE2 Agile?

Options:

A.

Because it explains how a small company can grow using traditional technologies

B.

Because it is designed to manage projects, delivering products in timeboxes

C.

Because it enables agile to be used in challenging and uncertain situations

D.

Because running a project and setting up a new business are the same

Buy Now
Questions 30

What should the business case state about the minimum viable product (MVP)?

Options:

A.

When the MVP will be defined

B.

That the MVP must go into operational use

C.

What the MVP is

D.

That the MVP is the same as project viability

Buy Now
Questions 31

Which well-known agile method uses visualization, and controls work in progress?

Options:

A.

Scrum

B.

Lean Startup

C.

Lean

D.

Kanban

Buy Now
Questions 32

Which of the following is a benefit of an organization being and doing agile?

Options:

A.

Faster time-to-market

B.

Using agile techniques

C.

Focusing on completing tasks

D.

Setting all tolerances to zero

Buy Now
Questions 33

Which artifact provides a list of user stories?

Options:

A.

Project backlog

B.

Project canvas

C.

Product backlog

D.

Release map

Buy Now
Questions 34

Which organizational level is responsible for day-to-day management and decision making within the constraints established by the project manager?

Options:

A.

Commissioning

B.

Directing

C.

Managing

D.

Delivering

Buy Now
Questions 35

Which statement about the ‘accept that the customer doesn’t need everything’ target is correct?

Options:

A.

It gives confidence on the progress of the project

B.

It can result in the early delivery of a minimum viable product

C.

It allows misunderstandings to be dealt with appropriately

D.

It is achieved by managing the culture of the team carefully

Buy Now
Questions 36

Which statement about the ‘keep teams stable’ target is CORRECT?

Options:

A.

It applies primarily to the long term, such as a project or a program

B.

It is the primary reason why the tolerance for cost is set to zero

C.

It prevents compromising the overall quality level of the product

D.

It results in the early delivery of a minimum viable product

Buy Now
Questions 37

Which of the following integrated elements defines who is working on the project and who is affected by the project?

Options:

A.

The project context

B.

The PRINCE2 practices

C.

The PRINCE2 processes

D.

The “people” element

Buy Now
Questions 38

How is the “closing a project” process used?

Options:

A.

By controlling the link between the project manager and the delivery team

B.

By ensuring that the project is viable

C.

By accepting the project product

D.

By ensuring the focus remains on delivering the stage’s products

Buy Now
Questions 39

Whose interests are specifically represented by the senior supplier?

1. Those ensuring the project is value for money.

2. Those who will use the project’s products.

3. Those who will be developing the project’s products.

4. Those responsible for the project’s technical integrity.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 40

Which of the following is used to monitor progress?

Options:

A.

Delegation matrix

B.

Swarming

C.

T-shirt sizing

D.

Burn-down chart

Buy Now
Questions 41

Which statement describes the focus of “being Agile” and not “doing Agile”?

Options:

A.

Task completion within strict timelines

B.

Adaptability and collaboration

C.

Document-driven processes

D.

Agile techniques for efficiency

Buy Now
Questions 42

When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?

Options:

A.

How to adapt the PRINCE2 management products

B.

How to select which Agile framework should be favoured

C.

How to decide whether PRINCE2 is appropriate

D.

How to calculate the project budget and cost tolerance

Buy Now
Questions 43

What should be included when transitioning from a project to business as usual to ensure continual improvement?

Options:

A.

Providing access to Kanban or team boards

B.

Establishing regular feedback loops

C.

Agreeing applicable Service Level Agreements (SLAs)

D.

Defining Key Performance Indicators (KPIs)

Buy Now
Questions 44

Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?

Options:

A.

To use empiricism, based on knowledge that comes from experience

B.

To build, measure, learn from your experiences

C.

To create a minimum viable product to manage uncertainty

D.

To fail fast, if you are going to fail

Buy Now
Questions 45

What should be decided when configuring PRINCE2 effectively?

Options:

A.

What to remove and where to add guidance

B.

Where to put the emphasis and where to add guidance

C.

What to significantly change to create the right blend

D.

Which areas are not enabled to work with agile

Buy Now
Questions 46

What is the purpose of the 'progress' practice?

Options:

A.

To provide a forecast for the project's viability

B.

To identify and assess opportunities and threats

C.

To identify the user needs and requirements

D.

To establish accountability for the project

Buy Now
Questions 47

When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?

Options:

A.

Preferable

B.

Typical

C.

Effective

Buy Now
Questions 48

When should PRINCE2 Agile be used?

Options:

A.

When a team is created to deliver a specific product

B.

When delivering an ongoing service to a customer

C.

When an established team performs product maintenance

D.

When simple requests to update a product are implemented

Buy Now
Exam Name: PRINCE2 Agile Foundation (Version 2) Exam
Last Update: Feb 7, 2026
Questions: 162
PRINCE2-Agile-Foundation pdf

PRINCE2-Agile-Foundation PDF

$25.5  $84.99
PRINCE2-Agile-Foundation Engine

PRINCE2-Agile-Foundation Testing Engine

$30  $99.99
PRINCE2-Agile-Foundation PDF + Engine

PRINCE2-Agile-Foundation PDF + Testing Engine

$40.5  $134.99