Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?
Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?
In its simplest form, what is the main drawback of critical path method scheduling?
Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?
How many workdays occur from the start of the Product Testing to the Product Available milestone?
Determine the correct formula and date for the late start for the Activity 11001:
Which of these letters, symbols or words best approximates the graphical shape of a project's cumulative BCWS?
If Activity E's duration changes to 4 months, what is the overall duration of the project.
In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?
During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?
Using the normal schedule, what is the early finish date and total float of Activity 10002?
Project schedules help control all of the following EXCEPT for_____________________.
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity
Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?
What day would Activity C complete if the duration of Activity B was reduced to zero?
The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.
Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?
Which of the following is NOT required when performing weekly or monthly schedule updates?
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?