Special Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: clap70

CFM Certified Facility Manager Questions and Answers

Questions 4

A project sponsor indicates that a project should build a facility at the lowest cost, in the least time, and with the highest quality. What should the project manager do?

Options:

A.

Work with the sponsor to refine the project charter with more feasible constraints

B.

Implement the project with the given constraints, as instructed by the project sponsor

C.

Inform the project sponsor that a lower-quality project will be provided

D.

Inform the project sponsor that the project cannot proceed with the given constraints

Buy Now
Questions 5

What are the three steps in conducting a risk assessment?

Options:

A.

Identification, analysis, and evaluation.

B.

Analysis, consultation, and review.

C.

Consultation, identification, and treatment.

D.

Likelihood, consequence, and rating.

Buy Now
Questions 6

What method is used for recording a facility's characteristics, such as utility use and waste stream, to measure and monitor processes in place?

Options:

A.

Sustainability audit

B.

Quality control

C.

Sustainability plan

Buy Now
Questions 7

Which bond is returned to contractors who submit unsuccessful proposals?

Options:

A.

Performance

B.

Bid

C.

Retention

Buy Now
Questions 8

As a facility manager, what is the most basic maintenance and operation responsibility that you must meet?

Options:

A.

Ensure positive tenant relationships

B.

Provide a safe and clean environment

C.

Maintain a detailed log of all maintenance activities

D.

Align the facility management plan with corporate objectives

Buy Now
Questions 9

During the construction phase of a project you are managing, the customer wishes to add to the project scope. You think that the cost of the change is 25% greater than your contingency. What steps will you take?

Options:

A.

Get an estimate from the contractor for a change order. Also, review the impact this will have on the entire project’s cost, schedule, quality, and risks. Present these findings to the customer along with the request for additional funds.

B.

Tell the customer you may be able to accommodate their request if the contingency budget is not used for other issues. Try to cut other scope items or create savings in other parts of the project to fully fund this request.

C.

Tell the customer that their request is out of scope and cannot be accommodated. The project does not have the funds for this additional work. Explain how this request impacts schedules delaying work and adding significantly to time as well as cost.

D.

Immediately agree to add the work to your project scope without getting an estimate from the contractor to determine the additional cost. You and the contractor can work out the differences as you go along.

Buy Now
Questions 10

Your senior leadership decided to implement an energy dashboard to track utility consumption. They want a baseline before commissioning has started to evaluate the results. How should this commissioning information be used on the dashboard?

Options:

A.

To show the month's utility usage after commissioning and guide decisions on installing additional equipment.

B.

To show how much energy comes from the grid and how much from renewable sources.

C.

To show changes in energy usage as commissioning projects are completed and determine whether the project achieved the desired outcomes.

D.

To show monthly kilowatts used by individual pieces of equipment.

Buy Now
Questions 11

What is the definition of physical vacancy?

Options:

A.

Percentage of units that are unoccupied and available for lease

B.

Spaces occupied but in delinquencies

C.

Percentage of units that are occupied but are not producing income

D.

Leasable space that is used for other purposes or is otherwise impossible to lease

Buy Now
Questions 12

Who implements the strategic facility plan?

Options:

A.

Operations Manager

B.

Facility Manager

C.

Chief Financial Officer

D.

Chief Operations Officer

Buy Now
Questions 13

What is referenced when demonstrating how a facility management project is directly linked to a corporation's long-range plan, outlining its broad, high-level goals?

Options:

A.

Success criteria

B.

Project charter

C.

Strategic facility plan

D.

Real estate master plan

Buy Now
Questions 14

What functionality enables a Building Automation System (BAS) to support energy management during peak demand periods?

Options:

A.

Thermal coupling

B.

Capacity management

C.

Load shedding

D.

Cycle management

Buy Now
Questions 15

As the Facility Manager, you secured 5,500 square feet of Class A office space on a multi-tenant floor to support a two-year business initiative. To minimize capital investment, the space will be used with pre-existing furnishings, fixtures, and equipment. However, before you can move people into this space, you will need a certificate of occupancy. What system must be examined to obtain a certificate of occupancy?

Options:

A.

Life safety system

B.

Potable water system

C.

Network connections

D.

Telephone system

Buy Now
Questions 16

When is the BEST time for a facility manager to offer suggestions on a project at minimal cost?

Options:

A.

Upon completion of the project

B.

Throughout the project

C.

Early in the design development process

D.

After the drawings and prices are finalized

Buy Now
Questions 17

Recently, an organization has flattened its structure versus that of a typical pyramid structure. As part of the restructure, the existing office building will be renovated. What type of design elements should a facility manager consider in the renovation?

Options:

A.

Offices for management, teaming areas, shorter workstation panels, and large conference rooms

B.

Team areas, bigger workstations for files, offices for senior management, and fewer meeting rooms

C.

Space for employee interaction, team areas, smaller workstations, and shorter panels

Buy Now
Questions 18

What is the most important strategic issue in the relationship between facility requirements and organizational requirements?

Options:

A.

Coordination

B.

Alignment

C.

Understanding

Buy Now
Questions 19

What is a good reason to get the facilities engineers involved early in the planning of a new building design or major renovation?

Options:

A.

To create operational and energy usage benchmarks at the beginning of the project

B.

To ensure that the as-built drawings are accurate

C.

To ensure that the design optimizes the operations and maintenance of the proposed building systems

D.

To ensure that all punch list items have been adequately addressed

Buy Now
Questions 20

A residential complex next to a facility manager's building has complained about light trespassing from the campus area. What is the BEST action to take to minimize the amount of light that escapes from your property?

Options:

A.

Remove some of the lights closest to the residential complex.

B.

Reduce the fixture's height, angling, and shield the fixtures to decrease glare.

C.

Reduce the wattage in the exterior lighting fixtures.

D.

Move the offending light fixtures away from that area.

Buy Now
Questions 21

When would an organization choose a lease with a purchase option?

Options:

A.

When tax rebates cannot be applied.

B.

When it lacks the initial capital for the purchase.

C.

When it has long-term plans to develop the real estate.

D.

When it needs to partner with a developer.

Buy Now
Questions 22

In planning your operating budget for the next fiscal year, what should NOT be included?

Options:

A.

Quarterly belt and filter changes

B.

Preventive maintenance during annual shutdown

C.

Electrical utility costs

D.

Allowance to overhaul the system’s motors that will soon be inoperative

Buy Now
Questions 23

A facility manager is responsible for this year's renovation projects. The Vice President has indicated that it is critical to develop and adhere to space and furniture standards while meeting corporate needs within budget. One of the most important projects is the renovation of four floors of a building which will house the Finance and Sales and Marketing Departments. In meeting with the management of each department, a list of needs that they expect in the renovations has been compiled. Some of the needs are easily met within corporate standards, while other needs would require unique solutions. The facility manager has been able to meet most needs of both departments and has also explained to the management of each department why all needs cannot be met.

A week after both departments move, the Vice President calls the facility manager and states employees in Sales and Marketing and Finance have indicated that they are dissatisfied with their space and that the facility manager was not responsive to their needs.

How should the facility manager verify that the groups are dissatisfied and rectify the situation?

Options:

A.

Review all the materials received on the project to verify space was built per the scope of work.

B.

Do a formal review of the project including various staff levels to get an understanding of the complaints and create an action plan to resolve them.

C.

Have some water cooler discussions to gather information about the negative comments and make adjustments accordingly.

D.

Do nothing, move on to the next project, and make an effort to avoid the problem in the future.

Buy Now
Questions 24

What is the process of limiting a company's exposure to liability?

Options:

A.

Risk management.

B.

Risk avoidance.

C.

Liability management.

D.

Limited liability analysis.

Buy Now
Questions 25

Which task should occur during the first phase of sustainable plan development?

Options:

A.

Assign members to assist with developing a business case

B.

Review preliminary business cases

C.

Define what criteria will be used to consider and evaluate ideas

D.

Develop cash flow

Buy Now
Questions 26

Your company is evaluating a commercial office building for a new acquisition. What documents are the most important to review during the due diligence process?

Options:

A.

Current building as-built drawings

B.

Local building codes

C.

Current tenants' leases

Buy Now
Questions 27

What is the BEST way to acknowledge acceptance of completed project deliverables?

Options:

A.

Scope control

B.

Scope definition

C.

Scope verification

D.

Scope planning

Buy Now
Questions 28

What describes a facility condition assessment?

Options:

A.

A report detailing the sustainability goals of an organization

B.

A five to ten-year facility plan incorporating owned and leased space

C.

An inspection and analysis of energy flows in a building with the objective of understanding energy efficiency

D.

A report of the current state of a building and component systems

Buy Now
Questions 29

What is the most important feature of an Integrated Workplace Management System (IWMS)?

Options:

A.

Use of software that allows ease of use.

B.

Use of standards that allow integration.

C.

Use of hardware that allows mobility.

Buy Now
Questions 30

How should rainwater from a hospital roof be used?

Options:

A.

Domestic, such as bathing.

B.

Dishwashing in the kitchen.

C.

Landscape maintenance.

D.

Medical process rinses.

Buy Now
Questions 31

A company's data center is being relocated to a different building. Who should be hired to ensure that the new location is properly prepared when the equipment arrives?

Options:

A.

An HVAC consultant who has experience with renovations.

B.

The vendor who is providing the computer equipment.

C.

An electrical engineer who has experience in the industry.

D.

A consultant who has experience relocating data centers.

Buy Now
Questions 32

A new hire has been provided with new uniforms and a $150 stipend for work boots. Within the first month, the employee gives a two-week notice. What actions should the manager take?

Options:

A.

Ask in a thoughtful and respectable tone for the employee to reimburse the organization for the uniforms and work boots.

B.

Absorb the loss of the material in the operating budget under uniform depreciation.

C.

Refer to the employee handbook and follow organizational policy regarding uniform and work boot issuances to employees.

Buy Now
Questions 33

What is the fourth stage in a well-established model of team development that consists of forming, storming, and norming?

Options:

A.

Adjourning

B.

Completing

C.

Reporting

D.

Performing

Buy Now
Questions 34

When posting required signage for fire emergencies, which message is the MOST immediate?

Options:

A.

Location of First Aid kits

B.

Location of emergency exits

C.

Location of AED with directions for its use

Buy Now
Questions 35

What action should you take to address the premature aging of a roofing membrane?

Options:

A.

Plan and budget for replacing the roof system as soon as possible to prevent degradation or damage to other building components and contents.

B.

File a warranty claim with the manufacturer based on the membrane’s failure to reach its expected service life.

C.

Extend the service life of the roofing membrane with patches and repairs as leaks are detected until the full expected service life of the membrane is realized.

D.

Explain to occupants that water infiltration is expected in any facility and it will be addressed as an ongoing maintenance and repair item.

Buy Now
Questions 36

A company is ready to sign a lease for a new location. The new space must be renovated before workstations can be moved. The facility manager is asked to provide the occupancy date. Why is providing the occupancy date information critical?

Options:

A.

The moving company must be scheduled.

B.

The occupancy date represents when the company must begin paying rent.

C.

The date cannot be changed once the lease is signed.

D.

The facility manager will lose credibility if the information provided is incorrect.

Buy Now
Questions 37

What is the PRIMARY purpose of the Incident Command System (ICS)?

Options:

A.

Respond to large incidents.

B.

Avoid duplication of efforts in any incident.

C.

Effectively respond to any incident.

D.

Meet the needs of large operational staff.

Buy Now
Questions 38

Both the facility and IT managers are asked to assign staff to work together on a major project. Halfway through the project, a power struggle emerges due to divergent views. How should the managers initially intervene?

Options:

A.

Reestablish meeting guidelines

B.

Reassign additional members from each department

C.

Reassign project managers

Buy Now
Questions 39

When are the laws of supply and demand relative to price?

Options:

A.

When demand exceeds supply, prices drop

B.

Price is the only factor that limits the supply

C.

When demand exceeds supply, prices rise

D.

If supply exceeds demand, prices rise

Buy Now
Questions 40

A facility manager wants to implement a centralized work request center for facility requests. After market research, the facility manager finds several different ways to prioritize requests. Which criteria should be used to prioritize work requests?

Options:

A.

Job classification, total cost, complexity.

B.

Criticality, safety, complexity.

C.

Criticality, total cost, completion time.

D.

Criticality, material cost, complexity.

Buy Now
Questions 41

Which technology would be BEST to notify facility occupants during an emergency?

Options:

A.

Company's social media profile.

B.

Emergency notification system.

C.

E-mail system.

D.

Incident management system.

Buy Now
Questions 42

What may be impacted if requirements aren't captured correctly at the beginning of an Integrated Workplace Management System (IWMS) implementation?

Options:

A.

Cost and schedule

B.

Temperature control and cost

C.

Special relations and utilizing color

Buy Now
Questions 43

You work for a facilities management service provider that wants to improve its service delivery processes and has decided to analyze its performance data. What advice would you offer regarding the data analysis exercise?

Options:

A.

Have an independent consultant analyze the data.

B.

Only analyze data that relates to subpar performance.

C.

Only analyze data that is less than twelve months old.

D.

Use the data that is valid and relevant.

Buy Now
Questions 44

What key requirements should you make sure a contractor possesses when evaluating whether to award a contract?

Options:

A.

Capability and capacity to complete the project; supplemental insurance; and, qualified, licensed and trained staff.

B.

Capability and capacity to complete the project; required insurance and bonds; and, qualified, licensed and trained staff.

C.

Required insurance and bonds; professional trade association membership; and, qualified, licensed and trained staff.

D.

Required insurance and bonds; well-maintained equipment; and, qualified, licensed and trained staff.

Buy Now
Questions 45

As a result of a market assessment, your company has decided that the best and highest use for a currently vacant building in an industrial park would be as a manufacturing facility. In order for a facility to be considered as a best and highest use, it must pass a series of four tests. What is one of the four tests?

Options:

A.

Must be part of the strategic plan.

B.

Must be physically possible.

C.

Must be part of the real estate master plan.

D.

Must be strategically located.

Buy Now
Questions 46

You have been informed about a heavy water leakage, but you are away from town. How would you guide the on-site staff?

Options:

A.

Advise staff to scan the building to isolate the water leak. They should also evacuate people from the area of the leak.

B.

Direct staff using the facility master plan, as-built layout drawings, and the BMS to identify the source of the leak.

C.

Direct the staff to immediately call in a contractor.

Buy Now
Questions 47

A landlord has just completed a major capital improvement in a multi-tenant commercial building. The property manager is responsible for determining if the costs of the project can be recovered from the tenants. What is NOT part of the process?

Options:

A.

Checking each lease to determine if capital costs are recoverable

B.

Splitting costs evenly and charging all costs in the year when the project was performed

C.

Determining how much should be recovered each year and for how many years

D.

Determining if a finance charge gets added to the recoverable costs

Buy Now
Questions 48

You work for an organization that puts a strong emphasis on corporate values and being the employer of choice; truly valuing their people. The organization has put a lot of time and effort into ensuring that policies and procedures are in place to create an environment where employees are valued. This includes the company's performance appraisal system. How do you ensure the employees meet the expectations of the organization as well as your expectations?

Options:

A.

The organization will provide the format for performance reviews, including how often they occur. Set performance measures with employees and review with them according to the organization policy.

B.

Conduct an annual performance review as specified by HR. Have the employees develop a list of goals for themselves, taking into account the organization's objectives for next year.

C.

Develop performance measures and have the employees confirm their goals in writing and send monthly reports on progress towards their goals, including any issues they are facing.

D.

Set performance measures that are specific, measurable, and realistic. Tie these performance measures to department and organizational goals. Conduct monthly coaching sessions to review progress with the employees and provide coaching as needed to keep them on track.

Buy Now
Questions 49

An organization is considering relocating from leased building #1 into leased building #2. Leased building #1 is 55,000 sq. ft. costing $1,100,000 annually. Leased building #2 is 50,000 sq. ft. costing $1,100,000 annually. Building #1 can house 500 people and building #2 can house 580 people. The company's benchmark is $2,000.00 per person per year for leased space. What is the MOST important reason to know what the company's benchmarks are?

Options:

A.

It allows other organizations to measure against your results.

B.

It structures your recommendations in a method your managers require.

C.

It provides a quantitative measure to support your recommendations and decisions.

D.

It simplifies the budgeting process.

Buy Now
Questions 50

What is the PRIMARY purpose of the Incident Command System (ICS)?

Options:

A.

Coordinate effective response to any incident.

B.

Coordinate response to large incidents.

C.

Avoid duplication and provide better coordination efforts in any incident.

Buy Now
Questions 51

When can fire doors inside buildings be propped open?

Options:

A.

Can only be propped open during the day

B.

Cannot be left propped open at any time

C.

Need to be locked when they are not in use

Buy Now
Questions 52

What is the benefit of documenting lessons learned for projects?

Options:

A.

Provides inputs to the project issue log

B.

Summarizes the effect of decisions made on a project and serves as a guide for what to repeat and what to avoid in future projects

C.

Provides key inputs to create the project charter, develop the project management plan, and finalize the stakeholder register

Buy Now
Questions 53

What is MOST important when creating a facility culture of safety and security?

Options:

A.

Relying on a risks and hazards assessment after an incident has occurred

B.

Evaluating potential hazards and implementing corrective action, if needed

C.

Involving only senior management in the risk assessment

D.

Focusing exclusively on near misses

Buy Now
Questions 54

Successful emergency communication includes accurate information. What else should it include?

Options:

A.

Limited information based on situational awareness.

B.

A sense of urgency of the required action.

C.

Speculative details of the situation.

Buy Now
Questions 55

A recently installed speed bump that slows traffic for pedestrian safety in the facility parking lot is diverting water runoff away from the drain and toward an adjacent property. What factors should the facility manager consider when fixing the drainage problem?

Options:

A.

The facility manager’s responsibility ends at the property line, and no decision is necessary.

B.

Use water runoff as an irrigation source and control parking lot traffic.

C.

Pedestrian safety supersedes stormwater runoff issues, and no decision is necessary.

D.

Ensure pedestrian safety and resolve stormwater runoff issues.

Buy Now
Questions 56

How should the facility manager ensure the gym meets staff expectations?

Options:

A.

Solicit staff asking for suggestions on how to improve the gym.

B.

Poll in the industry and ask them how best to create and maintain a gym facility for staff use.

C.

Have the facility manager perform the monthly inspections.

D.

Hire a consultant to provide you with information regarding trends to keep a gym current.

Buy Now
Questions 57

Departments often forget to budget for equipment design and installation costs. What is the best solution?

Options:

A.

Develop a procedure that would charge back capital installation costs to the department procuring the equipment.

B.

Mark up each equipment capital request by 15% to cover design and installation costs.

C.

Establish a procedure for all capital budgets to include Facilities' input on design and installation costs.

D.

Create a facilities installation fund that is 15% of the company’s annual capital equipment fund to cover these costs.

Buy Now
Questions 58

You are a Facility Manager overseeing a proposed renovation of a floor to meet the needs of the business. What step should be taken first?

Options:

A.

Conduct space programming analysis.

B.

Perform a gap analysis.

C.

Engage an architect for scenario alternatives.

D.

Undergo a feasibility study.

Buy Now
Questions 59

What sequential steps should you follow when trying to settle a contract dispute with a contractor?

Options:

A.

Mediation, arbitration, litigation, and negotiation

B.

Mediation, negotiations, arbitration, and litigation

C.

Negotiations, mediation, arbitration, and litigation

D.

Negotiations, arbitration, mediation, and litigation

Buy Now
Questions 60

What is the MOST effective tool in managing change?

Options:

A.

Managing resistance.

B.

Anticipating user denial.

C.

Using surveys.

D.

Communication.

Buy Now
Questions 61

What is churn in a building?

Options:

A.

The term used for frequency of occupancy moves in a facility

B.

The flow of fresh air through the office

C.

The method of deciding who occupies a given space or cubicle

Buy Now
Questions 62

After completing a renovation of a wing of an older building, what actions will a Facility Manager do prior to occupancy to remove pollutants from the newly installed finishes?

Options:

A.

Adjust the HVAC.

B.

Run the building's air conditioning for a legally required period.

C.

Bring 100% fresh air into the area.

Buy Now
Questions 63

There has been a recent increase in complaints of items stolen from people's desks within a facility. What is the facility manager's initial step regarding the security of the staff and facility?

Options:

A.

Install security cameras throughout the facility to ensure you capture future incidents.

B.

Update your security procedures to ensure that staff maintain a secure desk.

C.

Investigate each case and remind staff to ensure all valuables are locked.

D.

Turn the matter over to a professional security company to lead an investigation.

Buy Now
Questions 64

What level of damage and risk is anticipated with the current building code requirements for most buildings?

Options:

A.

Buildings will have minor damage and occupants can continue to occupy the building after an event.

B.

Buildings will have very little or no damage with no impact on the occupancy and operations.

C.

Buildings will have damage but will not collapse and allow time for occupants to leave the building.

Buy Now
Questions 65

How is the Facility Condition Index (FCI) determined?

Options:

A.

Dividing the cost of deficiencies by the facility replacement value.

B.

Subtracting the facility replacement value by the cost of deficiencies.

C.

Dividing the facility replacement value by the cost of deficiencies.

D.

Multiplying the cost of deficiencies by the facility replacement value.

Buy Now
Questions 66

You provide integrated facility services for a client with multiple mixed-use sites. This includes all services except the client's core business. Your annual business review includes identifying the most cost-effective and productive ways to meet your client's needs. What is an effective way to track your client's needs?

Options:

A.

Direct facility staff to share feedback they receive while working around the sites

B.

Meet with your client regularly to report results and identify emerging needs

C.

Meet with client department heads and solicit their suggestions and observations about the services

Buy Now
Questions 67

Various workers in a facility are complaining about neck, shoulder, and back pain. The facility manager decides to execute an ergonomic audit. What is the primary purpose of an ergonomic audit?

Options:

A.

Identify new requirements for ergonomic equipment.

B.

Improve worker productivity.

C.

Identify existing problems and prevent future injuries.

D.

Determine a training program for the workers.

Buy Now
Questions 68

What should the FM department do in the ongoing monitoring of a newly outsourced Property Management contract?

Options:

A.

Explain the evaluation methodology based on the identified Key Performance Indicators.

B.

Include opportunity for the Contractor to respond to non-compliances.

C.

Ensure that all codes and regulations are met.

D.

Create an incentive program for innovative work.

Buy Now
Questions 69

During a large real estate project, what are the expenses of planning, design, construction, operation, maintenance, and disposition of a structure over time known as?

Options:

A.

Life-cycle costing.

B.

Investment analysis.

C.

Time value of money.

D.

Project classification.

Buy Now
Questions 70

What are the three parts of a security program?

Options:

A.

Law enforcement, physical devices, and procedures

B.

Law enforcement, personnel, and physical devices

C.

Procedures, physical devices, and executive management engagement

D.

Personnel, physical devices, and procedures

Buy Now
Questions 71

A facility manager has an employee who is highly creative and provides a web-based solution for many projects, even when it is not a solution for the customer. The facility manager needs to support innovation while still holding the employee accountable for business needs. Which action can be taken to support both innovation and customer requirements?

Options:

A.

Provide feedback from customers

B.

Provide quality training

C.

Review solutions in advance of work

D.

Coach on recognition of business needs

Buy Now
Questions 72

What tool can be used to help determine whether a specific change strategy will produce promised results?

Options:

A.

A GAP analysis

B.

A feasibility study

C.

A customer survey

Buy Now
Questions 73

Who defines quality within a facility?

Options:

A.

Facility manager

B.

Service contract provider

C.

Facility team

D.

Customer

Buy Now
Questions 74

Both the facility and information technology managers are asked to assign staff to work together on a major project. Halfway through the project, the managers observe that the team is in a win-lose power struggle because of divergent views among team members. How should the facility and information technology managers initially intervene?

Options:

A.

Reestablish meeting guidelines

B.

Reassign project managers

C.

Assign new team members who have similar personalities

D.

Assign additional members from each department to foster more problem-solving

Buy Now
Questions 75

Your organization is considering relocating from leased building #1 into leased building #2. Leased building #1 is 55,000 sq. ft. costing $1,100,000 annually. Leased building #2 is 50,000 sq. ft. costing $1,100,000 annually. Building #1 can house 500 people and building #2 can house 580 people. Your company's benchmark is $2,000.00 per person per year for leased space. Which building has a lower cost per sq. ft.?

Options:

A.

Building #1 has a lower cost per sq. ft.

B.

Building #1 and Building #2 are the same cost per sq. ft.

C.

Building #1 has a lower cost per person.

D.

Building #2 has a lower cost per sq. ft.

Buy Now
Questions 76

A chargeback system for electrical power use is being proposed as a means to encourage reduced consumption and to lower utility costs. What approach might be MOST equitable in attaining this goal?

Options:

A.

Charge departments based on net area occupied.

B.

Negotiate the individual chargeback rate with each department.

C.

Charge departments for their equipment based on their headcount as a percentage of total site headcount.

D.

Install sub-meters for each department as a basis for chargeback.

Buy Now
Questions 77

What is one way, as a Facility Manager, you can contribute to your company's ESG goals?

Options:

A.

Support continued education for your staff

B.

Implement quality control measurements in your operation

C.

Source materials and parts from companies that have fair pay and living wage standards

D.

Reduce spend by eliminating spare part inventories

Buy Now
Exam Code: CFM
Exam Name: Certified Facility Manager
Last Update: Apr 2, 2025
Questions: 251
CFM pdf

CFM PDF

$25.5  $84.99
CFM Engine

CFM Testing Engine

$30  $99.99
CFM PDF + Engine

CFM PDF + Testing Engine

$40.5  $134.99