If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?
Which are purposes of the quality theme?
1. To implement continuous improvement during the project
2. To establish how the project will ensure that products created will be acceptable to key stakeholders
3. To ensure that the project is desirable and achievable
4. To identify, assess and control uncertainty
Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?
Which are objectives of the 'managing a stage boundary' process?
1. To control the link between the people managing the project and the people producing the products
2. To approve requests for change received during the completed stage
3. To provide information to the project board on the performance of the current stage
4. To review and, if necessary, update the project management team structure and role descriptions
Which PRINCE2 principle helps to address a concern that the project team may NOT have worked on a similar project?
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?
Identify the missing words in the following sentence.
When proposed changes [ ? ], the change authority must refer the decision back to the project board.
To meet the minimum requirements for applying the progress theme, what must be considered?
Which approach must be followed as a minimum requirement for applying the plans theme?
Which role is responsible for the quality of the specialist products delivered in the project?
In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?
Identify the missing words in the following sentence.
The project manager [ ? ] for day-to-day management of the project.
Identify the missing word in the following sentence.
The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.
Which role is responsible for ensuring the project is justified in terms of cost?
Which role is responsible for appointing the senior user in a project that is independent from a program?
Which process provides information for the project board to review a completed stage and confirm continued business justification?
Which member of the project management team should secure funding for the project before the project stars?
Which action contributes to achieving the ‘ensure continued business justification’ principle?
The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual
products being worked on.
Which part of effective issue management is the project manager applying?
in the ‘starting up a project’ process, what is the PRINCE? name for a ‘request for proposal’ received by an external supplier?
According to the 'manage by exception’ principle, which statement about tolerances is CORRECT?
Which common project context relates to the need to engage with external suppliers to deliver part of the project?
In which step of the risk management’ technique should the organization's environment be considered?
What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?
Which should define how tools will be used to support the information needs of the project team?
Which role is responsible for focusing on the safety and well-being of the project team?
Which term is defined as the means by which an organization transitions to a desired future state?
Which feature of a stage plan suggests that a project is in danger of scope creep?
The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.
Which element of effective business case management is the senior user applying?
As part of the 'business case management’ technique, how is the business case maintained during the project lifecycle?
According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?
The project board needs to review whether the investment remains justified as the project progresses according to plan.
Which principle is being applied by the ‘business case' practice when the project board undertakes this review?
How should effective issue management be applied When changing management products?
Which TWO are objectives of the 'closing a project’ process?
1. To confirm to the project board that each stage’s products are approved
2. To review whether the project was delivered within time and cost tolerances
3. To confirm whether operational staff are happy to take ownership of the products
4. To confirm that there is authority to close the project
The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the ‘quality management technique should this occur?
Which TWO are objectives of the ‘starting up a project’ process?
1. To create a common view of How the required quality will be achieved
2.To give authority to initiate the project
3. To appoint the resources needed to do the work to initiate the project
4. To ensure that projects are initiated based or agreed acceptance criteria for the project product.
The project manager needs to confirm that operational teams are responsible for the running of the outputs.
During which step of the ‘organizational design and development’ technique should the project manager ensure this?
Which is one of the six aspects of project performance that needs to be managed?
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
What is the collective name for individuals or groups who may be affected by a project?
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
Which theme establishes the mechanisms to control against baselines by providing a forecast for the project's objectives and continued viability?
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
Which term is defined-as the amount and type or risk that the business is willing to take in pursuit of is objectives?
What should be recorded in a quality register?
1. Activities to ensure the products are fit for purpose
2. Identified threats and opportunities
3. Problems and concerns to be managed informally
4. Roles responsible for reviewing the project's products
Where can people who join a project after initiation quickly and easily find information about how the project is being managed?
Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE to a project:
Which role should be accountable for approving these proposals?
According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?
When developing a business case, the project manager reviewed the end project report from & previous similar project that stated had been underestimated on the project.
Which principle is being applied by the project manager when reviewing this information?
What is a goal of the 'implement' step within the recommended risk management procedure?
How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?
Identify the missing word in the following sentence relating to one of the principles:
A PRINCE2 project should have [?] defined for each project objective.
Identify the missing words in the following sentence.
The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.
Which statement about the length of management stages in a project is CORRECT?
Which TWO are objectives of the ‘controlling a stage process?
1. To focus attention on achieving Work Within) the agree tolerances
2. To create follow on action recommendations for all open issues and risks
3. To understand how the quality required will be achieved
4. To ensure that the stage’s products meet-agreed quality expectations
What should be implemented using a risk budget?
1. A request for change
2. A contingent plan
3. Actions to avoid a risk from occurring
4. Responses to dis-benefits
Identify the missing words in the following sentence.
PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.
The project board needs to confirm that there is enough information to initiate the project.
What should the project board review?
Which action should the project manager take during the 'assessing issues' step?
Which report must be used to inform the project board of a predicted deviation from agreed stage limits?