Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: geek65

Prince2-Foundation PRINCE2 7 Foundation written Exam Questions and Answers

Questions 4

Which describes an off-specification?

Options:

A.

An interdependency between products that was previously unidentified

B.

The addition of an improvement to a product description

C.

A prototype demonstrating a possible design solution

D.

The production of more than the defined quantity of a specialist product

Buy Now
Questions 5

Which is a purpose of the Risk theme?

Options:

A.

Establish a procedure to ensure every change is agreed by the relevant authority before it takes place

B.

Establish a cost-effective procedure to identify, assess and control uncertainty

C.

Establish mechanisms to control any unacceptable deviations from plan

D.

Establish mechanisms to manage risks at the corporate or programme level of an organization

Buy Now
Questions 6

If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?

Options:

A.

Appointing the project board and producing the project brief

B.

Planning the initiation stage and appointing the project manager

C.

Producing the additional role descriptions and validating the project product description

D.

Verifying the project approach and capturing previous lessons

Buy Now
Questions 7

Which theme provides all management levels within the project management team with mechanisms for monitoring and control?

Options:

A.

Progress

B.

Change

C.

Organization

D.

Quality

Buy Now
Questions 8

Which are purposes of the quality theme?

1. To implement continuous improvement during the project

2. To establish how the project will ensure that products created will be acceptable to key stakeholders

3. To ensure that the project is desirable and achievable

4. To identify, assess and control uncertainty

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 9

Which process monitors work that has been assigned to a team manager?

Options:

A.

Controlling a stage

B.

Directing a project

C.

Managing a stage boundary

D.

Managing product delivery

Buy Now
Questions 10

Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

Options:

A.

Manage by stages

B.

Manage by exception

C.

Continued business justification

D.

Learn from experience

Buy Now
Questions 11

Which is an objective of the 'initiating a project' process?

Options:

A.

To ensure that baselines are established and controlled

B.

To ensure that the business case is kept under review

C.

To ensure that the planned products are delivered within tolerances

D.

To ensure that user acceptance of the products is confirmed

Buy Now
Questions 12

Which are objectives of the 'managing a stage boundary' process?

1. To control the link between the people managing the project and the people producing the products

2. To approve requests for change received during the completed stage

3. To provide information to the project board on the performance of the current stage

4. To review and, if necessary, update the project management team structure and role descriptions

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 13

Which is a minimum requirement for applying the business case theme?

Options:

A.

To provide statements of actual benefits at benefits reviews

B.

To report on project performance at project closure

C.

To define the actions required to confirm the project's benefits are realized

D.

To monitor changes to the project plan to identify exceptions

Buy Now
Questions 14

Which PRINCE2 principle helps to address a concern that the project team may NOT have worked on a similar project?

Options:

A.

Defined roles and responsibilities

B.

Learn from experience

C.

Manage by exception

D.

Focus on products

Buy Now
Questions 15

Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

Options:

A.

Risk category

B.

Risk description

C.

Risk response

D.

Risk status

Buy Now
Questions 16

Identify the missing words in the following sentence.

When proposed changes [ ? ], the change authority must refer the decision back to the project board.

Options:

A.

are below the agreed change budget

B.

are objected to by team members

C.

are rejected by the change authority

D.

exceed the agreed change budget

Buy Now
Questions 17

Which theme estimates the cost of delivering the project?

Options:

A.

Business case

B.

Change

C.

Plans

D.

PROGEESS

Buy Now
Questions 18

Which is a minimum requirement for applying the organization theme?

Options:

A.

Each member of the project management team must have a written role description

B.

The roles of the project management team must be combined, wherever possible

C.

The project manager must be appointed from the supplier organization

D.

The frequency of communication to the project's stakeholders must be documented

Buy Now
Questions 19

Which is a purpose of the plans theme?

Options:

A.

To identify, assess and control any potential changes to the baseline

B.

To establish the project's structure of accountability

C.

To assess and control uncertainty

D.

To understand whether the targets are achievable

Buy Now
Questions 20

Which is a purpose of the 'directing a project' process?

Options:

A.

To exercise overall control over the project

B.

To take corrective action to control risks and issues

C.

To do the minimum in order to decide whether the project is feasible

D.

To update the project plan before the next stage

Buy Now
Questions 21

Which theme verifies that a project's products are fit for purpose?

Options:

A.

Business case

B.

Organization

C.

Quality

D.

Progress

Buy Now
Questions 22

To meet the minimum requirements for applying the progress theme, what must be considered?

Options:

A.

How lessons will be learned

B.

How time-driven reports will be produced

C.

Which management products will be baselined

D.

Who is responsible for reporting on progress

Buy Now
Questions 23

Which approach must be followed as a minimum requirement for applying the plans theme?

Options:

A.

Activity-based planning

B.

Product-based planning

C.

Agile

D.

Risk management

Buy Now
Questions 24

Within which integrated element does PRINCE2 set minimum requirements?

Options:

A.

Themes

B.

Processes

C.

Principles

D.

Project environment

Buy Now
Questions 25

What is a benefits management approach used to assess?

Options:

A.

How the project's products have performed when in operational use

B.

The effectiveness of the project strategies

C.

How the project has progressed against its plans

D.

The suitability of the project management team structure

Buy Now
Questions 26

Why is a Project Brief produced?

Options:

A.

To act as a trigger for the Starting up a Project process

B.

To record the strategies and management controls to be used by a project

C.

To provide a full and firm foundation for the initiation of a project

D.

To be used by the Project Board as a basis for reviewing the progress of a project

Buy Now
Questions 27

Which role is responsible for the quality of the specialist products delivered in the project?

Options:

A.

Executive

B.

Senior user

C.

Senior supplier

D.

Project assurance

Buy Now
Questions 28

In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?

Options:

A.

Directing a project

B.

Managing product delivery

C.

Managing a stage boundary

D.

Initiating a project

Buy Now
Questions 29

Identify the missing words in the following sentence.

The project manager [ ? ] for day-to-day management of the project.

Options:

A.

and the project board are responsible

B.

and the team manager(s) are accountable

C.

has responsibility

D.

decides who is responsible

Buy Now
Questions 30

Identify the missing word in the following sentence.

The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.

Options:

A.

activities

B.

processes

C.

products

D.

quality

Buy Now
Questions 31

Which role is responsible for ensuring the project is justified in terms of cost?

Options:

A.

Project manager

B.

Executive

C.

Senior user

D.

Senior supplier

Buy Now
Questions 32

Which role is responsible for appointing the senior user in a project that is independent from a program?

Options:

A.

The project manager

B.

The executive

C.

Corporate, program management or the customer

D.

Project assurance

Buy Now
Questions 33

Which process provides information for the project board to review a completed stage and confirm continued business justification?

Options:

A.

Controlling a stage

B.

Closing a project

C.

Directing a project

D.

Managing a stage boundary

Buy Now
Questions 34

Which member of the project management team should secure funding for the project before the project stars?

Options:

A.

Project executive

B.

Project manager

C.

Senior user

D.

senior supplier

Buy Now
Questions 35

What is a description of a leadership activity within a project?

Options:

A.

Understanding and working with different departments outside of the project team

B.

Agreeing a work package with a tear manager to deliver products using specific tools

C.

Ensuring that a co-located project team uses the agreed communication methods

D.

Creating a stage plan and product descriptions for the products to be created in the next stage

Buy Now
Questions 36

What is a description of a purpose of the ‘quality’ practice?

Options:

A.

To enable the project products to meet the documented expectations of the user

B.

To document fundamental information to make rational sneer (Wert commissioning the project

C.

To establish the basis for the project, to enable the work to deliver the project product to be understood

D.

To monitor the allocated work, deal with issues, and allocate additional work if required

Buy Now
Questions 37

Which action contributes to achieving the ‘ensure continued business justification’ principle?

Options:

A.

Producing separate business cases for each customer and supplier involved in the project

B.

Defining the products that the project must produce in order to control change effectively

C.

Establishing limits of authority on the project based on defined tolerances

D.

Adapting PRINCEZ to the scale of investment and the delivery approach

Buy Now
Questions 38

The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual

products being worked on.

Which part of effective issue management is the project manager applying?

Options:

A.

Baselines

B.

Change budget

C.

Change control

D.

Issue resolution

Buy Now
Questions 39

in the ‘starting up a project’ process, what is the PRINCE? name for a ‘request for proposal’ received by an external supplier?

Options:

A.

Project mandate

B.

Project brief

C.

Work package

D.

Project approach

Buy Now
Questions 40

Which is a definition of management?

Options:

A.

Instructing the execution of tasks in line with agreed ways of working

B.

Translating stakeholder requirements into quality criteria

C.

Assigning people with specific skills and capabilities to work on multiple projects

D.

Defining, assuring, and accepting products back into the business

Buy Now
Questions 41

According to the 'manage by exception’ principle, which statement about tolerances is CORRECT?

Options:

A.

Whenever authority is delegated to the project manager, the project board should set tolerances for the stage

B.

Whenever there is a forecast to exceed a tolerance, it should be escalated to the project board

C.

Whenever there is a forecast to exceed a tolerance, it should be resolved at the next monthly project board meeting

D.

Whenever authority is delegated to the team manager, the focus should be on delivering within time and cost tolerances

Buy Now
Questions 42

Which common project context relates to the need to engage with external suppliers to deliver part of the project?

Options:

A.

Commercial

B.

Delivery method

C.

Organizational

D.

Scale

Buy Now
Questions 43

When is a work breakdown structure MOST useful?

Options:

A.

When there are multiple work packages with a mix of internal and external resources

B.

in a simple project with one work package for the work of a small team

C.

When establishing a change authority aligned to project tolerances

D.

When assuring business, user and supplier aspects of project performance

Buy Now
Questions 44

In which step of the risk management’ technique should the organization's environment be considered?

Options:

A.

Identity

B.

Assess

C.

Plan

D.

Implement

Buy Now
Questions 45

How is uncertainty identified, assessed and controlled?

Options:

A.

By avoiding or reducing a threat

B.

By analysing the risk cause in detail

C.

By applying the risk practice

D.

By allocating a risk budget to the project

Buy Now
Questions 46

How does product-based planning help to determine the project approach?

Options:

A.

By Identifying the outputs that the project trust deliver

B.

By planning in detail how to deliver the outputs over a more predictable time scale

C.

By managing constraints to the planned completion date for the project

D.

By dividing the delivery of the project's outputs into stages which do not overlap

Buy Now
Questions 47

Which details the identified threats and Opportunities related in the project?

Options:

A.

Risk management approach

B.

Project plan

C.

Risk register

D.

Business case

Buy Now
Questions 48

What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?

Options:

A.

Benefits sustainability

B.

Product sustainability

C.

Delivery sustainability

D.

Quality sustainability

Buy Now
Questions 49

Which should define how tools will be used to support the information needs of the project team?

Options:

A.

Digital and data management approach

B.

Quality management approach

C.

Issue management approach

D.

Commercial management approach

Buy Now
Questions 50

Which should provide guidance on how and when prototyping is to be used?

Options:

A.

Product description

B.

Quality management approach

C.

Quality register

D.

Sustainability management approach

Buy Now
Questions 51

Which describes a management activity within a project?

Options:

A.

Encouraging a project team to continue working on a particularly challenging product

B.

Discussing project objectives with key stakeholders during a requirements gathering workshop

C.

Agreeing a work package with a team manager to deliver products within agreed tolerances

D.

Seeking feedback from team members to ensure they are still aligned to the project's objectives

Buy Now
Questions 52

Which role is responsible for focusing on the safety and well-being of the project team?

Options:

A.

Project executive

B.

Project board

C.

Project manager

D.

Team manager

Buy Now
Questions 53

Which term is defined as the means by which an organization transitions to a desired future state?

Options:

A.

Change management

B.

Risk management

C.

Issue management

D.

Communication management

Buy Now
Questions 54

Which feature of a stage plan suggests that a project is in danger of scope creep?

Options:

A.

Stage plans are prepared by the project manager as the stage comes to an end

B.

Products identified in a stage plan cannot be traced back to the project plan

C.

The team delivering the stage plan includes staff from different parts of an organization

D.

it is not possible to implement remedial actions for an exception by updating a stage plan

Buy Now
Questions 55

Why is change management important in a project?

Options:

A.

It provides clarity on how the culture of an organization needs to adapt over time

B.

It provides processes and management products to use when requesting a change

C.

It provides confidence that the project can meet is objectives and has continued business Justification

D.

It provides a controlled and bidirectional flow of information to key Influencers

Buy Now
Questions 56

What is a purpose of the ‘quality’ practice?

Options:

A.

To predict whether the project will deliver on time and to cost and whether the benefits will outweigh the costs

B.

To resolve off-specifications, that are Identified during the project, at the end of the project

C.

To plan the project so that there is time to deal with quality defects late in the project

D.

To identify the user's expectations and determine how the project will achieve them

Buy Now
Questions 57

When does the ‘directing a project’ process start?

Options:

A.

When the project manager submits the project brief for approval

B.

When the request to authorize a project is received

C.

After the project has been authorized by the business layer

D.

After the project mandate has been received

Buy Now
Questions 58

The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.

Which element of effective business case management is the senior user applying?

Options:

A.

Aligning products to business objectives and tolerances

B.

The business case lifecycle

C.

Establishing business justification

D.

Planning benefit reviews during the project

Buy Now
Questions 59

As part of the 'business case management’ technique, how is the business case maintained during the project lifecycle?

Options:

A.

By linking the outcomes and benefits to the business objectives included in the business case

B.

By updating the business case during each management stage, as actual costs are incurred

C.

By providing a robust justification for the entire project in a detailed business case

D.

By justifying to the project board that the project should be initiated

Buy Now
Questions 60

According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?

Options:

A.

Project executive AND senior user

B.

Senior supplier AND team manager

C.

Project executive AND project manager

D.

Project manager AND team manager

Buy Now
Questions 61

The project board needs to review whether the investment remains justified as the project progresses according to plan.

Which principle is being applied by the ‘business case' practice when the project board undertakes this review?

Options:

A.

Manage by exception

B.

Manage by stages

C.

Focus on products

D.

Tailor to suit the project

Buy Now
Questions 62

How should effective issue management be applied When changing management products?

Options:

A.

By changing the issue management approach at the end of each stage to reflect lessons

B.

By creating new versions of a management product when a change is approved

C.

By Implementing a change budget to fund changes to the project product

D.

By recording the required change to a management product as an off-specification

Buy Now
Questions 63

Which TWO are objectives of the 'closing a project’ process?

1. To confirm to the project board that each stage’s products are approved

2. To review whether the project was delivered within time and cost tolerances

3. To confirm whether operational staff are happy to take ownership of the products

4. To confirm that there is authority to close the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 64

What does qualitative analysis of a risk assess, as a minimum?

Options:

A.

How soon each risk might occur

B.

The fallback plan for each risk

C.

The likelihood and the effect of each risk on objectives

D.

The speed with which the effect of each risk will be felt

Buy Now
Questions 65

The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the ‘quality management technique should this occur?

Options:

A.

Gathering user inputs

B.

Accepting products

C.

Describing the quality management approach

D.

controlling quality

Buy Now
Questions 66

Which TWO are objectives of the ‘starting up a project’ process?

1. To create a common view of How the required quality will be achieved

2.To give authority to initiate the project

3. To appoint the resources needed to do the work to initiate the project

4. To ensure that projects are initiated based or agreed acceptance criteria for the project product.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 67

Which is an internal factor to consider when tailoring PRINCE??

Options:

A.

The safety legislation

B.

The environmental standards

C.

The industry's regulations

D.

The organization's procedures

Buy Now
Questions 68

The project manager needs to confirm that operational teams are responsible for the running of the outputs.

During which step of the ‘organizational design and development’ technique should the project manager ensure this?

Options:

A.

Manage the ongoing changes to the project ecosystem

B.

Transition the project into the organizational ecosystem

C.

Understand the organizational ecosystem

D.

Develop the project ecosystem

Buy Now
Questions 69

Who carries out audits that are independent of the project?

Options:

A.

Quality assurance

B.

Project Assurance

C.

Project Support

D.

Project Manager

Buy Now
Questions 70

Which is one of the six aspects of project performance that needs to be managed?

Options:

A.

Progress

B.

Change

C.

Risk

D.

Security

Buy Now
Questions 71

Which is a purpose of the Directing a Project process?

Options:

A.

Provide the information required to confirm if it is worthwhile to initiate a project

B.

Enable overall control of a project to be exercised by the Project Board

C.

Establish the level of control required by the Project Board after initiation.

D.

Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved

Buy Now
Questions 72

Which is a purpose of the Initiating a Project process?

Options:

A.

Decide if it is worthwhile to initiate a project

B.

Decide on the project approach

C.

Establish solid foundations for a project

D.

Identify the number of Work Packages required

Buy Now
Questions 73

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

Options:

A.

Create a separate Project Board to manage the supplier elements of the project

B.

Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.

C.

Create user and supplier groups

D.

Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board

Buy Now
Questions 74

What takes place during the Closing a Project process?

Options:

A.

The post-project benefits reviews are performed

B.

Ownership of the project's products is transferred to the customer

C.

An End Stage Report is prepared for the final stage

D.

The project closure notification is reviewed and approved

Buy Now
Questions 75

Which should be funded from a change budget?

Options:

A.

The Starting up a Project process

B.

A fallback plan

C.

An agreed change to the scope of a project

D.

A change to a plan, within allocated tolerances, due to poor estimating

Buy Now
Questions 76

From whom does a Team Manager obtain approval for a completed product?

Options:

A.

Project Manager

B.

Project Support

C.

The authority defined in the Product Description

D.

Senior Supplier

Buy Now
Questions 77

Which should be funded by a change budget?

Options:

A.

Increase in agreed scope

B.

Initiation stage

C.

Change Authority

D.

Handover activities

Buy Now
Questions 78

Whose approval is needed to replace a Stage Plan with an Exception Plan?

Options:

A.

Corporate or programme management

B.

Project Board

C.

Project Manager

D.

Team Manager

Buy Now
Questions 79

Which is a benefit of using PRINCE2?

Options:

A.

Enables the management of projects as well as of 'business as usual' activities

B.

Can be tailored by leaving out elements of the method for some projects

C.

Can be applied to any type of project

D.

Avoids the need to involve corporate or programme management

Buy Now
Questions 80

Which is NOT included in the PRINCE2 definition of a project?

Options:

A.

A project is a temporary organization

B.

A project's purpose is to deliver one or more business products

C.

A project is part of 'business as usual'

D.

A project is based on an agreed Business Case

Buy Now
Questions 81

Which is a difference between management and technical stages?

Options:

A.

Management stages require planning and technical stages do not

B.

Technical stages can overlap and management stages cannot

C.

Management stages deliver products and technical stages do not

D.

Technical stages require resources and management stages do not

Buy Now
Questions 82

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

Options:

A.

Progress

B.

Change

C.

Organization

D.

Quality

Buy Now
Questions 83

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

Options:

A.

Directing a Project

B.

Managing a Stage Boundary

C.

Controlling a Stage

D.

Starting up a Project

Buy Now
Questions 84

Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

Options:

A.

quality

B.

supplier

C.

risk

D.

product

Buy Now
Questions 85

Which is NOT a purpose of the Organization theme?

Options:

A.

Define a project management team structure

B.

Define the level of tolerance for each level of the project management team

C.

Define the Project Board's responsibility for directing the project

D.

Define which role is accountable for the project's success

Buy Now
Questions 86

Which is a true statement about acceptance criteria?

Options:

A.

Acceptance criteria are used to produce the customer's quality expectations

B.

Acceptance criteria are less specific and precise than customer's quality expectations

C.

Once agreed, acceptance criteria CANNOT be changed

D.

Acceptance criteria should be agreed between the customer and the supplier

Buy Now
Questions 87

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

Options:

A.

Manage by stages

B.

Manage by exception

C.

Continued business justification

D.

Learn from experience

Buy Now
Questions 88

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

Options:

A.

Directing a Project

B.

Controlling a Stage

C.

Managing a Stage Boundary

D.

Managing Product Delivery

Buy Now
Questions 89

What is an off-specification?

Options:

A.

A new requirement

B.

A quality tolerance

C.

A type of issue

D.

A major risk

Buy Now
Questions 90

What is the collective name for individuals or groups who may be affected by a project?

Options:

A.

Customers

B.

Project Support

C.

Stakeholders

D.

Team members

Buy Now
Questions 91

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

Options:

A.

Only corporate or programme management

B.

Only the Project Board

C.

Only the Project Manager

D.

All levels of management

Buy Now
Questions 92

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

Options:

A.

Corporate group

B.

Project Board

C.

Project Assurance

D.

Executive

Buy Now
Questions 93

Which is a true statement about PRINCE2 event-driven controls?

Options:

A.

Event-driven controls take place at predefined periodic intervals

B.

Event-driven controls are produced at the frequency defined in a Work Package

C.

Event-driven controls are used for decision making

D.

Checkpoint Reports are event-driven controls

Buy Now
Questions 94

Which risk response type is appropriate to respond to an opportunity?

Options:

A.

Accept

B.

Fallback

C.

Exploit

D.

Transfer

Buy Now
Questions 95

Which is a typical core activity within configuration management?

Options:

A.

Quality assurance

B.

Risk management

C.

Verification and audit

D.

Progress reporting

Buy Now
Questions 96

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

Options:

A.

Raise a request for change

B.

Raise an off-specification

C.

Write an Exception Report

D.

Amend the Work Package

Buy Now
Questions 97

Which process covers the work done by external suppliers who may NOT be using PRINCE2?

Options:

A.

Closing a Project

B.

Managing a Stage Boundary

C.

Managing Product Delivery

D.

Directing a Project

Buy Now
Questions 98

What is the first task of product-based planning?

Options:

A.

Produce the Initiation Stage Plan

B.

Write the Project Product Description

C.

Identify dependencies

D.

Create the product breakdown structure

Buy Now
Questions 99

Which is a purpose of the Controlling a Stage process?

Options:

A.

Produce a Team Plan for the work to be assigned to a Team Manager

B.

Select and implement actions that will resolve deviations from a plan within tolerance

C.

Obtain approvals for products delivered in a Work Package

D.

Update a Project Plan to incorporate the actuals from a Stage Plan

Buy Now
Questions 100

Which is a type of issue?

Options:

A.

A lesson

B.

A request for change

C.

An Exception Report

D.

A risk with an estimated high impact

Buy Now
Questions 101

Which is a purpose of the Managing Product Delivery process?

Options:

A.

Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package

B.

Provide a controlled link between the Project Manager and the Team Manager(s)

C.

Enable the Project Board to request updates to the current Team Plan

D.

Establish solid foundations for the project

Buy Now
Questions 102

Which is an objective of the Closing a Project process?

Options:

A.

Review and approve the plan for project closure

B.

Review the performance of the project against its baseline

C.

Perform any post-project reviews

D.

Create a Benefits Review Plan

Buy Now
Questions 103

Which theme establishes the mechanisms to control against baselines by providing a forecast for the project's objectives and continued viability?

Options:

A.

Business case

B.

Plans

C.

Change

D.

Progress

Buy Now
Questions 104

Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

Options:

A.

Stage Plan

B.

Communication Management Strategy

C.

Follow-on action recommendations

D.

Quality Management Strategy

Buy Now
Questions 105

Which term is defined-as the amount and type or risk that the business is willing to take in pursuit of is objectives?

Options:

A.

Risk appetite

B.

Opportunity

C.

Risk tolerance

D.

Risk cause

Buy Now
Questions 106

What should be recorded in a quality register?

1. Activities to ensure the products are fit for purpose

2. Identified threats and opportunities

3. Problems and concerns to be managed informally

4. Roles responsible for reviewing the project's products

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 107

Whitt is 3 purpose of the initiating a project’ process?

Options:

A.

To prepare the contract for the project to enable the project board to commit to delivery

B.

To provide the project board with Just Enough Information to decide whether to approve the Initiation stage

C.

To provide the opportunity for the senior user in confirm that they find the project product acceptable

D.

To enable the project board to empower the project manager to work within delegated authority limits

Buy Now
Questions 108

What process provides information on a team’s work to the project manager?

Options:

A.

Controlling a stage

B.

Directing a project

C.

Managing a stage boundary

D.

Managing product delivery

Buy Now
Questions 109

Where can people who join a project after initiation quickly and easily find information about how the project is being managed?

Options:

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Project product description

Buy Now
Questions 110

Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE to a project:

Which role should be accountable for approving these proposals?

Options:

A.

Project board

B.

Project manager

C.

Project assurance

D.

Business layer

Buy Now
Questions 111

Which principle helps to ensure that all changes to the outputs are agreed?

Options:

A.

Defined roles and responsibilities

B.

Focus on products

C.

Learn from experience

D.

Manage by exception

Buy Now
Questions 112

Which is an assumption about the PRINCE2 customer/supplier environment?

Options:

A.

The supplier will pay for the project

B.

The customer will provide the resources to deliver the products

C.

The customer will specify the desired result

D.

The supplier will tailor the project's application of PRINCE2

Buy Now
Questions 113

According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?

Options:

A.

They should be returned to corporate, programme management or customer

B.

They should be used to create an alternative business case for the project

C.

They should be transferred back to the project board to reassign

D.

They should be used to deliver a reduction in the scope of the project

Buy Now
Questions 114

Which is an objective of the 'directing a project' process?

Options:

A.

To create the plan to deliver the project product

B.

To select and appoint the project manager

C.

To design the project management team roles

D.

To give authority to deliver the project product

Buy Now
Questions 115

Which is a purpose of the 'initiating a project' process?

Options:

A.

To ensure the project has a sound basis before asking the project board to authorize the project

B.

To authorize the stage plan for the next management stage of the project

C.

To establish a contract between the project management team and the commissioning organization

D.

To ensure that prerequisites are in place before starting the project

Buy Now
Questions 116

How often should the 'controlling a stage' process be used during a project?

Options:

A.

Once, for the whole project

B.

For each delivery stage in the project

C.

Whenever the project board meets

D.

Twice, for initiation and for the rest of the project

Buy Now
Questions 117

When developing a business case, the project manager reviewed the end project report from & previous similar project that stated had been underestimated on the project.

Which principle is being applied by the project manager when reviewing this information?

Options:

A.

Learn from experience

B.

Tailor ta Suit the project

C.

Manage by stages

D.

Ensure continued business justification

Buy Now
Questions 118

Which describes a time-driven control?

Options:

A.

The dates for the project's end stage assessment included in the project plan

B.

The expected frequency of progress reports specified in a work package

C.

The expected dates for planned checks of specialist products included in a stage plan

D.

The planned exception assessment meeting to authorize a requested exception plan

Buy Now
Questions 119

What is a goal of the 'implement' step within the recommended risk management procedure?

Options:

A.

To prepare specific management responses to identified risks

B.

To monitor the effectiveness of actioned risk responses

C.

To estimate the risk to the project in terms of probability and impact

D.

To communicate information related to the risks faced by the project

Buy Now
Questions 120

Which is a benefit of applying the ‘tailor to suit the project’ principle?

Options:

A.

Project management becomes less bureaucratic

B.

The capability of leadership is strengthened

C.

The project environment complexity is reduced

D.

The number of outputs is reduced

Buy Now
Questions 121

Which is an objective of the ‘directing a project’ process?

Options:

A.

To tailor the project’s products and roles so that the project suits the circumstances

B.

To respond to the project mandate by starting up a project

C.

To provide an interface between the project and corporate management

D.

To ensure the stage products are delivered to the stated quality standards

Buy Now
Questions 122

What is the result of the change derived from using the project’s product?

Options:

A.

Benefit

B.

Dis-benefit

C.

Outcome

D.

Output

Buy Now
Questions 123

What is the change authority role permitted to authorize?

Options:

A.

Risks to the project

B.

Adjustments to the limits on the change budget

C.

Changes to stage tolerance

D.

Changes to the project that do not exceed a defined budget

Buy Now
Questions 124

How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?

Options:

A.

By providing a common understanding of the products required

B.

By providing the tolerances for the project manager’s objectives

C.

By providing roles descriptions for the project management team

D.

By providing the justification for the project

Buy Now
Questions 125

What is an advantage of applying the 'learn from experience' principle?

Options:

A.

It allows the project board to delegate cost tolerances to the project manager

B.

It allows the project team to fully understand their roles and responsibilities

C.

It allows the project manager to delegate time tolerances to the team managers

D.

It allows the project team to identify improvements to be made during the project

Buy Now
Questions 126

What is a purpose of the communication management approach?

Options:

A.

To define how the project team intends to obtain responses from stakeholders

B.

To describe the techniques required to make the project product acceptable to stakeholders

C.

To describe the target organizational state and how the business will move to that new state

D.

To describe the processes used to engage with stakeholders in identifying uncertainties

Buy Now
Questions 127

Identify the missing word in the following sentence relating to one of the principles:

A PRINCE2 project should have [?] defined for each project objective.

Options:

A.

themes

B.

principles

C.

processes

D.

tolerances

Buy Now
Questions 128

Identify the missing words in the following sentence.

The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.

Options:

A.

benefits, change, risk,

B.

benefits, quality, risk,

C.

change, quality, risk,

D.

benefits, change, quality,

Buy Now
Questions 129

What is a risk actionee responsible for?

Options:

A.

Identifying risks to the project that might occur in their department

B.

Owning and authorizing the use of the risk budget to fund risk responses

C.

Managing, monitoring and controlling of all aspects of an assigned risk

D.

Carrying out a risk response action to respond to a particular risk

Buy Now
Questions 130

Which activity is part of the recommended risk management procedure?

Options:

A.

Allocating a budget to investigate issues

B.

Reviewing risk management practices to ensure that they are performing effectively

C.

Sending information to stakeholders about risks to the projects

D.

Resolving conflicts between the project and the programme board

Buy Now
Questions 131

Which statement about the length of management stages in a project is CORRECT?

Options:

A.

A higher level of major risk will require a stage to be longer

B.

Stage length is influenced by project board availability

C.

A higher level of major risk will require a stage to be shorter

D.

Use of management stages represents a time driven control

Buy Now
Questions 132

Which TWO are objectives of the ‘controlling a stage process?

1. To focus attention on achieving Work Within) the agree tolerances

2. To create follow on action recommendations for all open issues and risks

3. To understand how the quality required will be achieved

4. To ensure that the stage’s products meet-agreed quality expectations

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 133

What should be implemented using a risk budget?

1. A request for change

2. A contingent plan

3. Actions to avoid a risk from occurring

4. Responses to dis-benefits

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 134

Identify the missing words in the following sentence.

PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

Options:

A.

corporate, programme management or the customer

B.

the project board

C.

the project manager

D.

the change authority

Buy Now
Questions 135

The project board needs to confirm that there is enough information to initiate the project.

What should the project board review?

Options:

A.

Project brief

B.

Business case

C.

Benefits management approach

D.

Project plan

Buy Now
Questions 136

What is an advantage of applying the 'manage by stages' principle?

Options:

A.

The PRINCE2 method can be used for any type of project

B.

The project delivers benefits that are aligned with strategic objectives

C.

The project has decision points so that it does not run on in an uncontrolled manner

D.

Tolerances can be defined for delegated authority

Buy Now
Questions 137

Which action should the project manager take during the 'assessing issues' step?

Options:

A.

Create an exception plan tor project board approval

B.

Gain project board feedback on the Issue priority

C.

Consider the impact of alternative options for resolution

D.

Determine the initial priority of the issue that has been raised

Buy Now
Questions 138

Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

Options:

A.

End stage report

B.

Checkpoint report

C.

Highlight report

D.

Exception report

Buy Now
Exam Code: Prince2-Foundation
Exam Name: PRINCE2 7 Foundation written Exam
Last Update: Nov 21, 2024
Questions: 461
Prince2-Foundation pdf

Prince2-Foundation PDF

$28  $80
Prince2-Foundation Engine

Prince2-Foundation Testing Engine

$33.25  $95
Prince2-Foundation PDF + Engine

Prince2-Foundation PDF + Testing Engine

$45.5  $130